(M/M/s/K Model). Leia is responsible for 13 data units in the IT offices in a small business called Data Wish. Each data unit runs on an average for 3 weeks and requires an average of ½ or 0.5 weeks to get reset by Leia before it start up again. If we assign the Poisson distribution to the "arrival" of each data unit for service and an exponentia distribution to the actual service provided, answer the following questions: a. The arrival rate would be units per week and the service rate would be per week. b. Calculate the following operating characteristics for the M/M/s/K system: Utilization Factor (p) % Performance Measures

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section12.5: Analytic Steady-state Queueing Models
Problem 9P
icon
Related questions
Question

Hi,

Pls help with steps and answers.

Thank you.

(M/M/s/K Model). Leia is responsible for 13 data units in the IT offices in a small business called Data Wish. Each
data unit runs on an average for 3 weeks and requires an average of ½ or 0.5 weeks to get reset by Leia before it can
start up again. If we assign the Poisson distribution to the "arrival" of each data unit for service and an exponential
distribution to the actual service provided, answer the following questions:
a. The arrival rate would be
units per week and the service rate would be
per week.
b. Calculate the following operating characteristics for the M/M/s/K system:
Utilization Factor (e)
%
Performance Measures
Transcribed Image Text:(M/M/s/K Model). Leia is responsible for 13 data units in the IT offices in a small business called Data Wish. Each data unit runs on an average for 3 weeks and requires an average of ½ or 0.5 weeks to get reset by Leia before it can start up again. If we assign the Poisson distribution to the "arrival" of each data unit for service and an exponential distribution to the actual service provided, answer the following questions: a. The arrival rate would be units per week and the service rate would be per week. b. Calculate the following operating characteristics for the M/M/s/K system: Utilization Factor (e) % Performance Measures
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing