MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 20X2 $150,000 20X1 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied. 2. Record the preceding transactions in MSK's books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 26E
icon
Related questions
Question
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was
completed in 20x2. Information relating to the contract follows:
20X2
$150,000
20X1
Costs incurred during the year
Estimated additional cost to complete
Billings during the year
Cash collections during the year
$290,000
145,000
260,000
240,000
265,000
285,000
Required:
1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure
the extent to which its performance obligation has been satisfied.
2. Record the preceding transactions in MSK's books assuming it recognizes revenue at a point in time when control of the completed
factory is transferred to the customer at the end of the project.
Transcribed Image Text:MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 20X2 $150,000 20X1 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied. 2. Record the preceding transactions in MSK's books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Knowledge Booster
Accounting for Intangible assets
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage