Net Present Value-Unequal Lives Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $651,283. net cash flows estimated for the two proposals are as follows: Net Cash Flow Year Processing Mill Electric Shovel 1 $222,000 $278,000 198,000 258,000 198,000 238,000 4 158,000 244,000 120,000 6 100,000 7 87,000 87,000 The estimated residual value of the processing mill at the end of Year 4 is $280,000. Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 0.943 0.909 0.893 0.870 0.833 0.890 0.826 0.797 0.756 0.694 0.840 0.751 0.712 0.658 0.579 4 0.792 0.683 0.636 0.572 0.482 0.747 0.621 0.567 0.497 0.402 0.705 0.564 0.507 0.432 0.335 7. 0.665 0.513 0.452 0.376 0.279 0227 0222 Previous Ne

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter12: Capital Investment Analysis
Section: Chapter Questions
Problem 21E: Net present value-unequal lives Bunker Hill Mining Company has two competing proposals: a processing...
icon
Related questions
Question
TakeASsighmentMain.do?invoker=&takeAssignmentSessionLocator=&inprogress%3false
еВook
Print Item
87,000
The estimated residual value of the processing mill at the end of Year 4 is $280,000.
Present Value of $1 at Compound Interest
Year
6%
10%
12%
15%
20%
1
0.943
0.909
0.893
0.870
0.833
0.890
0.826
0.797
0.756
0.694
0.840
0.751
0.712
0.658
0.579
4
0.792
0.683
0.636
0.572
0.482
5
0.747
0.621
0.567
0.497
0.402
0.705
0.564
0.507
0.432
0.335
0.665
0.513
0.452
0.376
0.279
8.
0.627
0.467
0.404
0.327
0.233
9
0.5
0.424
0.361
0.284
0.194
10
0.558
0.386
0.322
0.247
0.162
Determine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present
value table appearing above.
Processing Mill
Electric Shovel
Present value of net cash flow total
Less amount to be invested
%24
Net present value
%24
Which project should be favored?
Check My Work 3 more Check My Work uses remaining.
( Previous
Next
Transcribed Image Text:TakeASsighmentMain.do?invoker=&takeAssignmentSessionLocator=&inprogress%3false еВook Print Item 87,000 The estimated residual value of the processing mill at the end of Year 4 is $280,000. Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 0.890 0.826 0.797 0.756 0.694 0.840 0.751 0.712 0.658 0.579 4 0.792 0.683 0.636 0.572 0.482 5 0.747 0.621 0.567 0.497 0.402 0.705 0.564 0.507 0.432 0.335 0.665 0.513 0.452 0.376 0.279 8. 0.627 0.467 0.404 0.327 0.233 9 0.5 0.424 0.361 0.284 0.194 10 0.558 0.386 0.322 0.247 0.162 Determine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present value table appearing above. Processing Mill Electric Shovel Present value of net cash flow total Less amount to be invested %24 Net present value %24 Which project should be favored? Check My Work 3 more Check My Work uses remaining. ( Previous Next
eBook
Print Item
Net Present Value-Unequal Lives
Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $651,283. The
net cash flows estimated for the two proposals are as follows:
Net Cash Flow
Year
Processing Mill
Electric Shovel
1
$222,000
$278,000
198,000
258,000
3
198,000
238,000
158,000
244,000
120,000
100,000
87,000
8.
87,000
The estimated residual value of the processing mill at the end of Year 4 is $280,000.
Present Value of $1 at Compound Interest
Year
6%
10%
12%
15%
20%
1
0.943
0.909
0.893
0.870
0.833
0.890
0.826
0.797
0.756
0.694
3
0.840
0.751
0.712
0.658
0.579
4.
0.792
0.683
0.636
0.572
0.482
0.747
0.621
0.567
0.497
0.402
6
0.705
0.564
0.507
0.432
0.335
7.
0.665
0.513
0.452
0.376
0.279
0227
0222
0.404
Previous
Nex
Check My Work 3 more Check My Work uses remaining.
Cubmit Asignment for C
Transcribed Image Text:eBook Print Item Net Present Value-Unequal Lives Bunker Hill Mining Company has two competing proposals: a processing mill and an electric shovel. Both pieces of equipment have an initial investment of $651,283. The net cash flows estimated for the two proposals are as follows: Net Cash Flow Year Processing Mill Electric Shovel 1 $222,000 $278,000 198,000 258,000 3 198,000 238,000 158,000 244,000 120,000 100,000 87,000 8. 87,000 The estimated residual value of the processing mill at the end of Year 4 is $280,000. Present Value of $1 at Compound Interest Year 6% 10% 12% 15% 20% 1 0.943 0.909 0.893 0.870 0.833 0.890 0.826 0.797 0.756 0.694 3 0.840 0.751 0.712 0.658 0.579 4. 0.792 0.683 0.636 0.572 0.482 0.747 0.621 0.567 0.497 0.402 6 0.705 0.564 0.507 0.432 0.335 7. 0.665 0.513 0.452 0.376 0.279 0227 0222 0.404 Previous Nex Check My Work 3 more Check My Work uses remaining. Cubmit Asignment for C
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Present Value
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Survey of Accounting (Accounting I)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning