Normal Time Crash Time Immediate Predecessor(s) Activity Normal Cost (S) Crash Cost () (days) (days) START 50 160 START B 40 2 160 START 70 3 190 100 AC A.C 11 20 10 30 7. 30 80 280 G. 7. 60 110 60 7. 120 EF G. H FINISH a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times isdays. (Enter your response as an integer)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
Normal Time
Immediate
Predecessor(s)
Crash Time
Activity
Normal Cost (5)
Crash Cost ()
(days)
(days)
START
A
50
160
START
B
4.
40
160
START
70
190
B
10
100
A C
A.C
D
11
20
E
30
30
F
80
7.
280
G
7.
50
4.
110
60
7.
120
EF
G. H
FINISH
a. Using the normal times for each activity, what is the earliest date you can complete the project?
The corresponding project duration using the normal times isdays. (Enter your response as an integer)
Transcribed Image Text:Normal Time Immediate Predecessor(s) Crash Time Activity Normal Cost (5) Crash Cost () (days) (days) START A 50 160 START B 4. 40 160 START 70 190 B 10 100 A C A.C D 11 20 E 30 30 F 80 7. 280 G 7. 50 4. 110 60 7. 120 EF G. H FINISH a. Using the normal times for each activity, what is the earliest date you can complete the project? The corresponding project duration using the normal times isdays. (Enter your response as an integer)
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,