odeHead Software Inc. is a software development company. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid $32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmer's hourly rate to increase to $40.00 per hour during the first week in May.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 16MC: When is the direct labor time variance favorable? A. when the actual quantity used is greater than...
icon
Related questions
icon
Concept explainers
Topic Video
Question

14. 

CodeHead Software Inc. is a software development company. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid $32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmer's hourly rate to increase to $40.00 per hour during the first week in May.

Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. If an amount is zero, enter "0" and choose "Not applicable" from the dropdown.

 

 

 

Required:
1. If the team had generated 4,650 lines of code according to the original plan, what would have been the labor time variance?
$1
2. What was the actual labor time variance as a result of generating 5,650 lines of code?
3. What was the labor rate variance as a result of the bonus?
4. Are there any performance-related issues that the labor time and rate variances fail to consider?
The labor rate and time variances
the number of errors in the code from programmer fatigue. A program that has
will require significant time for debugging at a later date. Thus, managers
the efficiency of doing the
work and also the quality of the work.
5. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming
demand in the first week of May, rather than paying out the bonus. If another employee was hired from the employment firm, what would have been
the labor time variance in the first week?
6. Which decision is better, paying the bonus or hiring another programmer?
Transcribed Image Text:Required: 1. If the team had generated 4,650 lines of code according to the original plan, what would have been the labor time variance? $1 2. What was the actual labor time variance as a result of generating 5,650 lines of code? 3. What was the labor rate variance as a result of the bonus? 4. Are there any performance-related issues that the labor time and rate variances fail to consider? The labor rate and time variances the number of errors in the code from programmer fatigue. A program that has will require significant time for debugging at a later date. Thus, managers the efficiency of doing the work and also the quality of the work. 5. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming demand in the first week of May, rather than paying out the bonus. If another employee was hired from the employment firm, what would have been the labor time variance in the first week? 6. Which decision is better, paying the bonus or hiring another programmer?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning