On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an original price of P2,000,000 to be completed on June 30, 2023 subject to penalty of P500,000 on the it becomes virtually certain that construction will not be completed on the date agreed upon. On January 1, 2022, the contract price increased by P2,500,000 due to the change in the design of the building requested by the customer. year 12/31/2021 12/31/2022 12/31/2023 Cumulative costs incurred as of the end of the year Estimated remaining cost to complete at the end of the year 600,000 900,000 3,075,000 1,025,000 3,780,000 420,000 What is the realized gross profit (loss) to be recognized by MARCOS Company for the year ended December 31, 2023 if the outcome of construction can be estimated reliably?

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 26E
icon
Related questions
Question
100%
On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an
original price of P2,000,000 to be completed on June 30, 2023 subject to penalty of P500,000 on the year
it becomes virtually certain that construction will not be completed on the date agreed upon. On January 1,
2022, the contract price increased by P2,500,000 due to the change in the design of the building requested
by the customer.
12/31/2021 12/31/2022 12/31/2023
Cumulative costs incurred as of the end of the year
600,000
900,000
3,075,000
1,025,000
3,780,000
420,000
Estimated remaining cost to complete at the end of the year
What is the realized gross profit (loss) to be recognized by MARCOS Company for the year ended December 31, 2023 if the
outcome of construction can be estimated reliably?
Transcribed Image Text:On January 1, 2021, MARCOS Company entered into a contract for the construction of a building at an original price of P2,000,000 to be completed on June 30, 2023 subject to penalty of P500,000 on the year it becomes virtually certain that construction will not be completed on the date agreed upon. On January 1, 2022, the contract price increased by P2,500,000 due to the change in the design of the building requested by the customer. 12/31/2021 12/31/2022 12/31/2023 Cumulative costs incurred as of the end of the year 600,000 900,000 3,075,000 1,025,000 3,780,000 420,000 Estimated remaining cost to complete at the end of the year What is the realized gross profit (loss) to be recognized by MARCOS Company for the year ended December 31, 2023 if the outcome of construction can be estimated reliably?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT