On January 1, 2019, Solid Company accepted a long-term construction project for an initial contract price of P2,000,000 to be completed on June 30, 2020. On January 1, 2020, the contract price was increased to P3,000,000 by reason of change in the design of the project. The outcome of the construction contract can be estimated reliably. The project was completed on December 31,2020 which resulted to penalty amounting to P400,000. The entity provided the following data concerning the direct costs related to the said project for 2019 and 2020:                                    2019                  2020 Costs during the year               880,000                   1,360,000 Remaining estimated costs to complete at year-end                  1,320,000      560,000                  1. What is the construction revenue for the year ended December 31, 2018?

Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 6P
icon
Related questions
Question

On January 1, 2019, Solid Company accepted a long-term construction project for an initial contract price of P2,000,000 to be completed on June 30, 2020. On January 1, 2020, the contract price was increased to P3,000,000 by reason of change in the design of the project. The outcome of the construction contract can be estimated reliably. The project was completed on December 31,2020 which resulted to penalty amounting to P400,000. The entity provided the following data concerning the direct costs related to the said project for 2019 and 2020:                                    2019                  2020

Costs during the year               880,000                   1,360,000

Remaining estimated costs to complete at year-end                  1,320,000      560,000               

 

1. What is the construction revenue for the year ended December 31, 2018?

 

2.What is the realized gross profit for the year ended December 31, 2020?

 

3.What is the balance of construction in progress on December 31, 2020?

Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
SWFT Essntl Tax Individ/Bus Entities 2020
SWFT Essntl Tax Individ/Bus Entities 2020
Accounting
ISBN:
9780357391266
Author:
Nellen
Publisher:
Cengage
Individual Income Taxes
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
SWFT Comprehensive Volume 2019
SWFT Comprehensive Volume 2019
Accounting
ISBN:
9780357233306
Author:
Maloney
Publisher:
Cengage
SWFT Individual Income Taxes
SWFT Individual Income Taxes
Accounting
ISBN:
9780357391365
Author:
YOUNG
Publisher:
Cengage
SWFT Comprehensive Vol 2020
SWFT Comprehensive Vol 2020
Accounting
ISBN:
9780357391723
Author:
Maloney
Publisher:
Cengage