Paris Banh Mi is in the process of opening a new location in downtown Atlanta and has found the following information for the activities needed below. Time is in minutes. Activity Preceding Activity Optimistic Time Most Likely Time Pessimistic Time A 4 8 10 B A 4 5 8 C A A 6 8 12 D B, C 8 9 16 E D 8 10 10 15 F D 2 5 8 G E, F 7 12 14 H G 3 7 9 G 2 11 13 H, I 1 6 11 What is the expected length of the project? (Same table as Q7 above so no need to rework it. Round to nearest tenth)
Q: The following payoff table shows profit for a decision analysis problem with two decision…
A:
Q: Given the following information, determine the project schedule that minimizes the total project…
A: The table indicates that the optimal project duration is 6 weeks. This is because it minimizes the…
Q: In a single-period model, if the demand is normally distributed with a mean of 97 and a standard…
A: The objective of the question is to find the optimal order quantity in a single-period model where…
Q: Table 24-1 Price Quantity Total Cost $10 10 $80 9 15 85 8 20 95 7 25 110 6 30 140 5 35 175 40 215…
A: Consider the following formulas: TR=P×Q MR=ΔQΔTR MC=ΔQΔTC If the firm produces 15 units of…
Q: Contribution Income Statement and Operating Leverage Willamette Valley Fruit Company started as a…
A: Step 1: Total sales quantity = 650,000 packsSelling price = $ 75Variable costs = $ 42Fixed costs = $…
Q: You have been asked to balance a flow shop assembly operation to achieve an output rate of 120 units…
A: The table data is shown below, TaskPredecessor(s)Duration (minutes)A---1.4B---1.2CA,…
Q: Carlisle Tire and Rubber, Inc., is considering expanding production to meet potential increases in…
A: The objective of the question is to determine the optimal decision for Carlisle Tire and Rubber,…
Q: Please answer
A: 1. Teamwork is not only about collaboration; it's a powerful tool that drives organizational success…
Q: Is it possible to say that, in the last five years, organisations have moved away from mass…
A: Over the past five years, there has indeed been a discernible shift in organizational production…
Q: 11. Shown below are the planning period's demand and the standard hours required for four products…
A: The total labor hours required by these four products will be obtained by multiplying units demanded…
Q: At the beginning of her discussion with the mayor, Ava does not even allow the mayor to make any…
A: The objective of the question is to identify the type of behavior Ava is exhibiting in her…
Q: Jerusalem Medical Ltd., an Israeli producer of portable kidney dialysis units and other medical…
A: Answer well explained above
Q: a. Develop an AON network for this problem. b. What is the critical path? c. What…
A: a. Develop an AON network for this problem:To develop the AON network, we need to identify the…
Q: Assuming unlimited demand, what would be the flow rate based on below information? It takes about 5…
A:
Q: The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 1 unit…
A: Summary:PartChildren PartDemand Lead timeST(1), U(1)2TV(2),W(2),X(1)1UY(1),Z(3)2V-2W-3X-1Y-2Z-2Based…
Q: Based on what you know about best practices in negotiations, what can Katherine and Alicia do to…
A: Designing a plan to facilitate future budgets amid a negotiation dialogue like what Alicia and Kate…
Q: Discuss how an organisation applies Strategic Planning -Framework and Models to improve their…
A: Strategic planning is an essential process that businesses use to set their direction and goals for…
Q: The computer lab at State University has a help desk to assist students working on computer…
A: Let's solve this problem step by step using queuing theory formulas. We'll assume the computer lab…
Q: Determine the Taxes Owing/Refund for the following taxpayer: Taxation Year: 2021 Name of Taxpayer:…
A: Federal Tax Brackets and Rates for 2021:15% on the first $49,02020.5% on the next $49,020 to…
Q: In production plan 1, if the number of workers required in January is 50 and February is 52, do we…
A: The number of workers that are necessary in February (52) is compared to the number of workers that…
Q: Assuming the process started empty, how long will it take to service 20 patients based on below…
A: Part 2: Approach to solving the question:To solve this problem, we first break down the process into…
Q: None
A: Total Quality Management (TQM) is a complete control approach that extends beyond mere first-rate…
Q: Week Day 1 2 3 4 Sunday 40 35 39 43 Monday 54 55 54 59 Tuesday 61 60 65 64 Wednesday 72 77 78 74…
A: Trends:There isn't a clear overall trend in the data across the week, but there are fluctuations.…
Q: 2. The contract has many uses, including in construction and insurance. A contract comes with a…
A: The objective of the question is to understand how to handle a contractual dispute in the…
Q: A daily newspaper is stocked by a coffee shop so its patrons can purchase and read it while they…
A: Please comment down for any doubt. I hope my answer helps you.
Q: *5. BagBoy makes a popular model pull cart for golfers. The company wants to determine the upcoming…
A: Now, let's solve this problem using Excel Solver. (a) **Interpretation of the solution:** The…
Q: address the issues/poblems that may occur with building the skyscraper in oklahoma. determine the…
A: Building a skyscraper in Oklahoma involves tackling various challenges unique to the region.…
Q: Assume material A calls out material B (qty per = 1). Material A has a stock quantity of 10.…
A: Step 1: Calculate the total requirement for material A. Total requirement for material A = Demand…
Q: S&OP Problems Module 10 VB (1) aw Design Layout References Mailings Review View Grammarly ody) 11 A…
A: Level Sales and Operations Plan Explained in DetailThis plan prioritizes a stable workforce and…
Q: The accompanying data file contains 20 observations for t and yt. Click here for the Excel Data File…
A: a. Exponential SmoothingFormula= αAt+(1-α)Ftb. Error=yt-esexample:68-59=…
Q: Need help on calculating control limits for x-bar and r-chart based on the samples below: Sample…
A: Certainly! Control charts are statistical tools used in quality control to monitor processes over…
Q: please answer
A: 1.Written communication is most effective where there is a need for a permanent record: This…
Q: Can you help with an essay of Advantages and disadvantages for the red cross
A: Detailed explanation: Advantagesvolunteerismglobal reachdisaster reliefneutral and…
Q: What are the key components of the strategic profit model? How can it be used to examine the effect…
A: Logistic management is the part of management that deals with managing the flow or movement of…
Q: Tombro Industries is automating one of its plants and developing a flexible manufacturing system. In…
A: Throughput Time (1-a):Identify relevant times: We need data on wait time, processing time, move…
Q: Problem 10-24 (Algo) A shirt manufacturer buys cloth by the 100-yard roll from a supplier. For…
A: To set up the c-chart, let's calculate the necessary parameters:1. Average number of irregularities…
Q: Which of the following is a pressure for performance that nonprofits are experiencing? A. Funders…
A: Correct Option:A. Funders and donors want to ensure a high social return on investment.The pressure…
Q: Determine the order quantity, reorder point, annual holding cost, and order cost, then assume a…
A: Order QuantityThe Economic Order Quantity (EOQ) formula is used to determine the optimal order…
Q: tation Skills ment 9 12 6 3 00:00 02 Hours MinuteSeconds OBJECTIVE QUESTIONS in Moderevi sigata,…
A: The objective of the question is to identify the correct meaning of the acronym 'FAB' in the context…
Q: The length of time between breakdowns of an essential piece of equipment is important in the…
A: Formula for Exponential DistributionCumulative probabilitiesP(X < x) = P(X < x) = 1 -…
Q: Which of the following is a trend underway in the nonprofit sector? A. Accountability and…
A: The question is asking to identify the current trends in the nonprofit sector among the given…
Q: Charlie's Pizza orders all of its pepperoni, olives, anchovies, and mozzarella cheese to be shipped…
A: Step 1:Given:Review Period (R) = 4Lead Time (L) = 3Weekly Demand (D) = 180Standard Deviation (σ) =…
Q: How has globalization affected project management?
A: Project management is the branch of management that deals with organizing and overseeing the…
Q: Use the information contained below to compress one time unit per move using the least cost method.…
A: Approach to solving the question: Step by step Detailed explanation: Paths in the project with their…
Q: Can you guys help me on this? Thank you!
A: There is much more to Human Resources (HR) than merely processing paperwork and paying employees.…
Q: The accompanying data file contains 20 observations for t and yt. Click here for the Excel Data File…
A: 1. To get the 3 moving average you need the 3 previous data:example:t4= (54+50+46) / 3t4= 150/3t4=…
Q: The German Association of Engineers clarified ethical priority when there might be a conflict…
A: The prioritization of national laws by the German Association of Engineers implies that in cases…
Q: Thought leaders can be developed and taught over time. A. True B. False
A: Part 2: Explanation:Step 1: Thought Leadership DefinitionThought leadership refers to individuals…
Q: The owner of Genuine Subs, Inc., hopes to expand the present operation by adding one new outlet. She…
A: Profit calculation and breakeven analysis are done before starting any project to determine ·…
Q: In operations management, what does JIT stand for? A) Just in Time B) Just in Transition C)…
A: Operation management involves supervising and designing, as well as engineering processes and…
Step by step
Solved in 2 steps
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G HDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000
- I need a detailed explanation and assistance to solve this problem: A company decides to plan a project, with activities, precedences and random duration statistics given in the following table: Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks) A none 2 5 9 B A 1 6 8 C A 3 5 12 D B 2 4 12 E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 * What method should be used? Compute the mean and variances for each activity and add them to the table above * Draw the project network and label the arcs with the activity name. * Assuming that the critical path is AàBàP1àEàGàH, compute the probability that this path duration is between 28 weeks and 32 weeks. * Assuming that the critical path is AàBàP1àEàGàH, compute the number of weeks within which the project will be completed with probability 0.95.You may need to use the appropriate technology to answer this question. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown. Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 5 6 B 2 4 6 C A, B 4 5 6 D A, B 8 10 11 E B 2 4 6 F C 1 2 3 G D 4 8 10 H D, F 7 9 11 I E, G, H 3 4 5 (b) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (c) Based only on the critical path, what is the estimated probability that the project can be completed in 27 or fewer days? (Round your answer to four decimal places.)Jordanne King, the project manager for Webjets International, Inc., compiled a table showing time estimates for each of the activities of a project to upgrade the company’s Web page, including optimistic, most likely, and pessimistic.a. Calculate the expected time, te, for each activity.b. Calculate the variance, s2, for each activity.Activity Optimistic (days) Most Likely (days) Pessimistic (days)A 3 8 19B 12 15 18C 2 6 16D 4 9 20E 1 4 7
- A small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE PREDECESSOR a m b A − 1 4 7 B − 2 5 14 C A 5 11 17 D B 3 9 15 E C 3 3 3 Part 2 a) Find the expected completion time for this project. The expected completion time for this project is (enter your response as a whole number). Part 3 b) What variance value would be used to find probabilities of finishing by a certain time? The…You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…A solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN): a. The expected project completion time for this problem is and the standard deviation is . b. There is a 0.95 probability that the project will be completed by weeks. Activity Expected time Variance Critical? A 10 0.36 Yes B 7 0.11 No C 7 0.25 No D 3 0.48 Yes E 5 1.60 Yes F 7 0.69 No G 2 3.69 Yes
- I need assistance with the following questions in: Project Scheduling. This is a follow up to a question answered earlier. Question 1) was answered. 1) A company decides to plan a project, with activities, precedences and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F 2) The company decided that the project in the previous problem has to be expedited in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting the project reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.…The information in the table below is available for a large fund-raising project. Activity Activity Times (days) Activity Cost ($) Immediate Predecessor A 3 100 None B 4 150 None C 2 125 A D 5 175 B E 2 150 B F 4 200 C, D G 6 75 C H 2 50 C, D, E I 1 100 E J 4 75 D, E K 5 350 F, G L 3 150 G, H, I M 4 400 I, J N 4 175 K, M O 1 200 H, M P 5 150 N, L, O Draw the precedence network diagram. Perform the CPM (Critical Path Method) and give the complete activity schedule table, the project completion time, and the critical path. Plot on the same graph the total project costs per day, starting from day one to the completion date, assuming the earliest start times and then assuming the latest start times. What implications does the time differential have for cash flows and project scheduling? Show step by step solutionA student club plans on holding a campus-wide event at the end of the semester. The activities that have to be completed, duration of each activity, and their sequence are listed in the table below: Duration Immediate Activity (weeks) Predecessor A 2 -- B 3 A C 1 A D 3 B E 4 D,C F 1 E b. What is the earliest start, earliest finish time, latest start, latest finish time for activity E? Earliest start time _______ Earliest finish time _______ Latest start time _________ Latest finish time ________ C What is the slack for Activity C? Slack for activity C ________