Precedent Activity Length (week) Sequential |Sequential Task Туре A. High level analysis B. Selection of hardware platform C. Installation and commissioning of hardware D. Detailed analysis of core modules E. Detailed analysis of supporting modules F. Programming of core modules G. Programming of supporting modules H. Quality assurance of core modules 1. Quality assurance of supporting modules J. Core module training K. Development and QA of accounting reporting L. Development and QA of management reporting M. Development of Management Information System N. Detailed training A 2 Parallel B Sequential Sequential |Sequential Sequential Sequential Sequential Parallel 2 A 2 D 2 D 3 E F G C,H 1 Parallel E Parallel E Sequential L Sequential I, J, K, M 1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION 4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS 5. WHEN WILL THE PROJECT BE COMPLETED?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter7: Nonlinear Optimization Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

I only need answer for number 4 and 5

Type Precedent
Activity
Task
Length
(week)
Sequential
Sequential
A. High level analysis
B. Selection of hardware platform
C. Installation and commissioning of hardware
D. Detailed analysis of core modules
E. Detailed analysis of supporting modules
F. Programming of core modules
G. Programming of supporting modules
H. Quality assurance of core modules
1. Quality assurance of supporting modules
J. Core module training
K. Development and QA of accounting reporting
L. Development and QA of management reporting
M. Development of Management Information
System
N. Detailed training
1
1
A
2
Parallel
B
|Sequential
Sequential
Sequential
Sequential
Sequential
Sequential
A
2
D
D
3
E
1
G
1
Parallel
C,H
1
Parallel
E
1
Parallel
E
1
Sequential
L
1
Sequential I, J, K, M
1. CREATE THE NETWORK DIAGRAM USING AON
2. DETERMINE THE NETWORK PATHS
3. DETERMINE THE CRITICAL PATH AND ITS DURATION
4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS
5. WHEN WILL THE PROJECT BE COMPLETED?
Transcribed Image Text:Type Precedent Activity Task Length (week) Sequential Sequential A. High level analysis B. Selection of hardware platform C. Installation and commissioning of hardware D. Detailed analysis of core modules E. Detailed analysis of supporting modules F. Programming of core modules G. Programming of supporting modules H. Quality assurance of core modules 1. Quality assurance of supporting modules J. Core module training K. Development and QA of accounting reporting L. Development and QA of management reporting M. Development of Management Information System N. Detailed training 1 1 A 2 Parallel B |Sequential Sequential Sequential Sequential Sequential Sequential A 2 D D 3 E 1 G 1 Parallel C,H 1 Parallel E 1 Parallel E 1 Sequential L 1 Sequential I, J, K, M 1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION 4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS 5. WHEN WILL THE PROJECT BE COMPLETED?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,