Problem #2 a) Develop a CPM diagram for the activities/relationships listed below (assume durations are in months). For each activity calculate the Early Start, Late Start, Early Finish, Late Finish, Total Float, and Free Float. Clearly identify the critical path for the project (hint: a highlighter would be a good tool to use). Label Duration Must Follow Operations

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Use legend to answer question.

Problem #2
a) Develop a CPM diagram for the
activities/relationships listed below (assume
durations are in months). For each activity calculate the Early Start, Late Start, Early
Finish, Late Finish, Total Float, and Free Float. Clearly identify the critical path for
the project (hint: a highlighter would be a good tool to use).
Label
ABCDEFGHISKLMNOPQRS
G
E
O
А
L
D
с
Р
Activity
Q
M
I
Duration
24735 torum ∞o a tr∞ bon 7
7
6
7
5
3
8
9
4
7
8
6
b) After developing
10
5
Must Follow
Operations
A
A
A
A
B
B
F
G
G
the project schedule (part a) the project owner comes to you and
says they'll add an extra $50,000 to your contract if you can shorten the project by
one month. You ask the project team to look at the activities and determine which
activities can be shorten and how much it would cost. They return with the following
activities and estimated cost to shorten the duration by 1 month.
C,G
Н,
F,J,K
D,K
E,K
M.N
N,O
L,O,P
Q,R
Cost to shorten duration by 1 month
$55,000
$25,000
$50,000
$60,000
$10,000
$50,999
$49,999
$70,000
Transcribed Image Text:Problem #2 a) Develop a CPM diagram for the activities/relationships listed below (assume durations are in months). For each activity calculate the Early Start, Late Start, Early Finish, Late Finish, Total Float, and Free Float. Clearly identify the critical path for the project (hint: a highlighter would be a good tool to use). Label ABCDEFGHISKLMNOPQRS G E O А L D с Р Activity Q M I Duration 24735 torum ∞o a tr∞ bon 7 7 6 7 5 3 8 9 4 7 8 6 b) After developing 10 5 Must Follow Operations A A A A B B F G G the project schedule (part a) the project owner comes to you and says they'll add an extra $50,000 to your contract if you can shorten the project by one month. You ask the project team to look at the activities and determine which activities can be shorten and how much it would cost. They return with the following activities and estimated cost to shorten the duration by 1 month. C,G Н, F,J,K D,K E,K M.N N,O L,O,P Q,R Cost to shorten duration by 1 month $55,000 $25,000 $50,000 $60,000 $10,000 $50,999 $49,999 $70,000
LEGEND:
ES
Early Start
Task ID
LS
Late Start
TF
Total Float
Duration
FF
Free Float
EF
Early Finish
LF
Late Finish
Transcribed Image Text:LEGEND: ES Early Start Task ID LS Late Start TF Total Float Duration FF Free Float EF Early Finish LF Late Finish
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…