Problem: The DPWH in its previous study for a proposed sanitary landfill site in Pampanga is planning to use a clay liner for the landfill. Tests were performed on a sample clay from a borrow site. It was deemed necessary to have a minimum clay liner thickness of 0.30 m. The following results were obtained in the laboratory test. Initial water level in standpipe Final water level in standpipe Diameter of standpipe Height of soil sample Diameter of soil sample Duration of test = 96 cm - 56 cm = 12 cm = 10.2 cm - 5.4 cm = 12 hours The project manager would like to determine the effectiveness of using on-site clay soils for the lining material if it is favorable. Tests were also performed on the site clay and the following results were obtained. Height of soil sample Diameter of soil sample Volume of water collected = 8 cm = 5 cm %3D = 75600 cm = 60 cm = 1050 hours Constant head Duration of test 39. Determine the coefficient of permeability of the borrow clay in cm/sec. a. 1.36 x 10* b. 2.36 x 10* c. 3.61 x 10* d. insufficient data e. none of the above

Principles of Geotechnical Engineering (MindTap Course List)
9th Edition
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Braja M. Das, Khaled Sobhan
Chapter17: Subsoil Exploration
Section: Chapter Questions
Problem 17.2P
icon
Related questions
Question

Answers:

39. 6.28x10-4 cm/s

40. 1.36x10-4 cm/s

41. 6.48 meters

Problem: The DPWH in its previous study for a proposed sanitary landfill site in Pampanga is
planning to use a clay liner for the landfill. Tests were performed on a sample clay from a borrow
site. It was deemed necessary to have a minimum clay liner thickness of 0.30 m. The following
results were obtained in the laboratory test.
Initial water level in standpipe
Final water level in standpipe
Diameter of standpipe
Height of soil sample
Diameter of soil sample
Duration of test
%3D
= 96 cm
- 56 cm
= 12 cm
= 10.2 cm
= 5.4 cm
= 12 hours
The project manager would like to determine the effectiveness of using on-site clay soils for the
lining material if it is favorable. Tests were also performed on the site clay and the following results
were obtained.
Height of soil sample
Diameter of soil sample
Volume of water collected
= 8 cm
= 5 cm
!3!
75600 cm
= 60 cm
%3D
Constant head
Duration of test
= 1050 hours
39. Determine the coefficient of permeability of the borrow clay in cm/sec.
a. 1.36 x 10*
b. 2.36 x 10*
c. 3.61 x 10*
d. insufficient data
e. none of the above
40. Determine the coefficient of permeability of the on-site clay in cm/sec.
c. 3.61 x 10*
d. insufficient data
a. 1.36 x 10*
b. 2.36 x 10
e. none of the above
41. Compute the thickness of the on-site clay which is equivalent to 0.3 meter of the borrow clay.
c. 4.36 cm
d. insufficient data
a. 6.48 cm
b. 6.48 m
e. none of the above
Transcribed Image Text:Problem: The DPWH in its previous study for a proposed sanitary landfill site in Pampanga is planning to use a clay liner for the landfill. Tests were performed on a sample clay from a borrow site. It was deemed necessary to have a minimum clay liner thickness of 0.30 m. The following results were obtained in the laboratory test. Initial water level in standpipe Final water level in standpipe Diameter of standpipe Height of soil sample Diameter of soil sample Duration of test %3D = 96 cm - 56 cm = 12 cm = 10.2 cm = 5.4 cm = 12 hours The project manager would like to determine the effectiveness of using on-site clay soils for the lining material if it is favorable. Tests were also performed on the site clay and the following results were obtained. Height of soil sample Diameter of soil sample Volume of water collected = 8 cm = 5 cm !3! 75600 cm = 60 cm %3D Constant head Duration of test = 1050 hours 39. Determine the coefficient of permeability of the borrow clay in cm/sec. a. 1.36 x 10* b. 2.36 x 10* c. 3.61 x 10* d. insufficient data e. none of the above 40. Determine the coefficient of permeability of the on-site clay in cm/sec. c. 3.61 x 10* d. insufficient data a. 1.36 x 10* b. 2.36 x 10 e. none of the above 41. Compute the thickness of the on-site clay which is equivalent to 0.3 meter of the borrow clay. c. 4.36 cm d. insufficient data a. 6.48 cm b. 6.48 m e. none of the above
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Lateral earth pressure distribution against retaining walls
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap…
Fundamentals of Geotechnical Engineering (MindTap…
Civil Engineering
ISBN:
9781305635180
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning