Question 1 (Network) a. The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates as follows: Time Estimates (weeks) Activity Description Position Recruiting Predecessor a m A 8 17 B System Development System Training Equipment training Manual System Test 3 12 15 C A 4 7 10 D A 5 8 23 В, С В, С E 1 1 1 Preliminary System Changeover Computer-Personnel Interface Equipment Modification Equipment testing System Debugging and Installation Equipment Changeover F 1 4 G D, E 3 6. 9. H. D, E 1 2.5 I H 1 1 1 F, G G, I J 2 K 8 11 Use the information in the table to answer the following questions i. Compute the expected activity completion time for each activity. ( ii. Construct a network showing the inter-relationship between the project activities. Also perform the forward and backward pass of the Critical Path Method (CPM) on your network. iii. When will the computerized accounting system be ready for use? iv. What is the critical path (the critical activities)? 3a7-NE

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question 1 (Network)
a. The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts
system. Bank management has determined the activities required to complete the project, the
precedence relationships of the activities, and activity time estimates as follows:
Time Estimates (weeks)
Description
Position Recruiting
Activity
Predecessor
a
m
A
8.
17
System Development
System Training
Equipment training
Manual System Test
B
3
12
15
C
A
4
7
10
A
5
8.
23
В, С
В, С
E
1
1
1
Preliminary System Changeover
Computer-Personnel Interface
Equipment Modification
Equipment testing
System Debugging and Installation
Equipment Changeover
F
1
4
13
G
D, E
3
6.
9.
H.
D, E
1
2.5
7
I
H
1
1
1
F, G
G, I
J
2
2
2
K
5
8
11
Use the information in the table to answer the following questions
i. Compute the expected activity completion time for each activity. (
ii. Construct a network showing the inter-relationship between the project activities. Also perform the
forward and backward pass of the Critical Path Method (CPM) on your network.
iii. When will the computerized accounting system be ready for use? ^
iv. What is the critical path (the critical activities)?
Transcribed Image Text:Question 1 (Network) a. The Consolidated Bank of Ghana (CBG) is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates as follows: Time Estimates (weeks) Description Position Recruiting Activity Predecessor a m A 8. 17 System Development System Training Equipment training Manual System Test B 3 12 15 C A 4 7 10 A 5 8. 23 В, С В, С E 1 1 1 Preliminary System Changeover Computer-Personnel Interface Equipment Modification Equipment testing System Debugging and Installation Equipment Changeover F 1 4 13 G D, E 3 6. 9. H. D, E 1 2.5 7 I H 1 1 1 F, G G, I J 2 2 2 K 5 8 11 Use the information in the table to answer the following questions i. Compute the expected activity completion time for each activity. ( ii. Construct a network showing the inter-relationship between the project activities. Also perform the forward and backward pass of the Critical Path Method (CPM) on your network. iii. When will the computerized accounting system be ready for use? ^ iv. What is the critical path (the critical activities)?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.