QUESTION # 2 You have received a request from EXE plc to provide a quotation for the manufacture of a specialized piece of equipment. This would be a one-off order, in excess of normal budgeted production. The following cost estimate has already been prepared.     Note ₤ Direct materials:       Steel 10 meter sq @ ₤ 5 /meter sq 1 50 Brass fittings   2 20 Direct Labour:       Skilled 25 hours @ ₤8/hour 3 200 Semi-skilled 10 hours @ ₤5/hour 4 50 Overhead 35 hours @ ₤10/hour 5 350 Estimating time   6 100 Administrative overheads Allocated @ 20% of production cost 7 154 Total cost     924 Profit @25% of total cost   231 Selling price     1155 Notes: The steel is regularly used, and has a current stock value of ₤5/ sq meter. There are currently 100 sq meters in stock. The steel is readily available at a price of ₤5.5 / sq meter. The brass fittings would have to be bought specifically for this job: a supplier has quoted the price of ₤20 for the fittings required. The skilled labour is currently employed by your company and paid at a rate of ₤8/ hour. If this job were undertaken it would be necessary either to work 25 hour overtime which would be paid at time plus one half or to reduce production of another product which earn a contribution of ₤13/hour. The semi skilled labour currently has sufficient paid idle time to be able to complete this work. The overhead absorption rate includes power costs which are directly related to machine usage. If this job were undertaken, it is estimated that the machine time required would be ten hours. The machines incur power costs of ₤0.75/hour. There are no other overhead costs which can be specifically identified with this job. The cost of the estimating time is that attributed to the four hours taken by engineers to analyse the drawings and determine the cost estimate given above. It is company policy to add 20% on to the production cost as an allowance against administration costs associated with jobs accepted. This is the standard profit added by your company as part of its pricing policy. REQUIRED: Prepare, on a relevant cost basis, the lowest cost estimate that could be used as the basis for a quotation. Explain briefly your reasons for using each value in your estimate. Also what factors need to be considered before quoting for this order?

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter8: Budgeting For Planning And Control
Section: Chapter Questions
Problem 28E: Refer to Exercise 8.27. At the end of the year, Meliore, Inc., actually produced 310,000 units of...
icon
Related questions
icon
Concept explainers
Question

QUESTION # 2

You have received a request from EXE plc to provide a quotation for the manufacture of a specialized piece of equipment. This would be a one-off order, in excess of normal budgeted production. The following cost estimate has already been prepared.

 

 

Note

Direct materials:

 

 

 

Steel

10 meter sq @ ₤ 5 /meter sq

1

50

Brass fittings

 

2

20

Direct Labour:

 

 

 

Skilled

25 hours @ ₤8/hour

3

200

Semi-skilled

10 hours @ ₤5/hour

4

50

Overhead

35 hours @ ₤10/hour

5

350

Estimating time

 

6

100

Administrative overheads

Allocated @ 20% of production cost

7

154

Total cost

 

 

924

Profit

@25% of total cost

 

231

Selling price

 

 

1155

Notes:

  1. The steel is regularly used, and has a current stock value of ₤5/ sq meter. There are currently 100 sq meters in stock. The steel is readily available at a price of ₤5.5 / sq meter.
  2. The brass fittings would have to be bought specifically for this job: a supplier has quoted the price of ₤20 for the fittings required.
  • The skilled labour is currently employed by your company and paid at a rate of ₤8/ hour. If this job were undertaken it would be necessary either to work 25 hour overtime which would be paid at time plus one half or to reduce production of another product which earn a contribution of ₤13/hour.
  1. The semi skilled labour currently has sufficient paid idle time to be able to complete this work.
  2. The overhead absorption rate includes power costs which are directly related to machine usage. If this job were undertaken, it is estimated that the machine time required would be ten hours. The machines incur power costs of ₤0.75/hour. There are no other overhead costs which can be specifically identified with this job.
  3. The cost of the estimating time is that attributed to the four hours taken by engineers to analyse the drawings and determine the cost estimate given above.
  • It is company policy to add 20% on to the production cost as an allowance against administration costs associated with jobs accepted.
  • This is the standard profit added by your company as part of its pricing policy.

REQUIRED:

Prepare, on a relevant cost basis, the lowest cost estimate that could be used as the basis for a quotation. Explain briefly your reasons for using each value in your estimate. Also what factors need to be considered before quoting for this order?

 

 

 

 

Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Budgeting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning