Question Mr Mustafa, manager of project RTS of Syarikat Aurora Sdn Bhd. Is in the process of designing a problem that is clients can use in the job-finding process. Some of the activities include preparing progress report, site inspections, documents validation and appointments to see prospective employers, researching companies and industries, and so on. Some of the information on the activities appears in the following table: Activity A B C D E F G H I J K 000m 96 10 9 6 14 10 6 4 1 Time (days) m 10 7 3 20 7 10 7 15 11 7 7 2 b 12 c) Determine ES,EE,LS, LF and slack time for each activity. ( d) Determine the critical path and project completion time. ( 9 4 30 8 11 10 16 13 8 8 4 Answer all questions below: a) Construct a PERT network for this problem. b) Determine the expected times and variances for each activity/ e) Determine the probability that the project will be finished in 70 days. f) Determine the probability that the project will be finished in 80 days. g) Determine the probability that the project will be finished in 90 days. Immediate Predecessors A с B,D,E B,D,E F F G,H IJ G,H

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question
Mr Mustafa, manager of project RTS of Syarikat Aurora Sdn Bhd. Is in the process of designing a
problem that is clients can use in the job-finding process. Some of the activities include preparing
progress report, site inspections, documents validation and appointments to see prospective
employers, researching companies and industries, and so on. Some of the information on the activities
appears in the following table:
Activity
A
B
C
D
E
F
G
H
I
J
K
L
a
8
6
3
10
6
9
6
14
10
6
4
1
Time (days)
m
10
7
3
20
7
10
7
15
11
7
7
2
b
12
9
4
30
8
11
10
16
13
8
8
4
Answer all questions below:
a) Construct a PERT network for this problem.
b) Determine the expected times and variances for each activity /
c) Determine ES,EE,LS,LF and slack time for each activity. (
d) Determine the critical path and project completion time. (
e) Determine the probability that the project will be finished in 70 days.
f) Determine the probability that the project will be finished in 80 days.
g) Determine the probability that the project will be finished in 90 days.
Immediate
Predecessors
A
C
B,D,E
B,D,E
F
F
G,H
I
G,H
Transcribed Image Text:Question Mr Mustafa, manager of project RTS of Syarikat Aurora Sdn Bhd. Is in the process of designing a problem that is clients can use in the job-finding process. Some of the activities include preparing progress report, site inspections, documents validation and appointments to see prospective employers, researching companies and industries, and so on. Some of the information on the activities appears in the following table: Activity A B C D E F G H I J K L a 8 6 3 10 6 9 6 14 10 6 4 1 Time (days) m 10 7 3 20 7 10 7 15 11 7 7 2 b 12 9 4 30 8 11 10 16 13 8 8 4 Answer all questions below: a) Construct a PERT network for this problem. b) Determine the expected times and variances for each activity / c) Determine ES,EE,LS,LF and slack time for each activity. ( d) Determine the critical path and project completion time. ( e) Determine the probability that the project will be finished in 70 days. f) Determine the probability that the project will be finished in 80 days. g) Determine the probability that the project will be finished in 90 days. Immediate Predecessors A C B,D,E B,D,E F F G,H I G,H
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.