Task No.  Task Name   Task Duration(Days)  Immediate Predecessor task 1 Preliminary system description  40  — 2 Develop specifications 100  1 3 Client approval 50  2 4 Develop input-output summary 60 2 5 Develop alarm list  40  4 6 Develop log formats  40 3, 5 7 Software definition 35  3 8 Hardware requirements 35  3 9 Finalize input-output summary 60  5, 6 10 Analysis performance calculations  70  9 11  Automatic turbine startup analysis 65  9 12 Boiler guides analysis 30  9 13  Fabricate and ship 200 10, 11, 12 14 Software preparation  80  7, 10, 11 15  Install and check 130  13, 14 16 Termination and wiring lists  30  9 17 Schematic wiring lists 60  16 18  Pulling terminals and cables  60  15, 17 19 Operational test  125  18 20 First firing  1  19   Therefore, Critical Path = 1-2-4-5-6-9-10-13-15-18-19-20 Note: tj is the original duration of task j; dj is the minimum duration of task j. Expediting Costs ($1,000) and Limits Task no.            current tj  min dj cost to decrease  tj by X days 2                                                   100       70    1.5x^1.8 6                                                        40       20  2x^2.0 7                                                          35   20   1.x^2.0 10                                                 70       40      1.8x^1.9 14                                              80     60  1.9x^1.6 15                                                 130   120      0.95x^2.7 19                                                  125       80   0.9x^2.9 Expediting tasks can be profitable and necessary to meet deadlines, although employees do not really like it. Task completion quality is a function of the task completion time, and we would like to have a high quality. This may conflict with our objective of maximizing profit. Because quality affects future revenues, it is difficult to estimate the dollar impact of poor quality. If  tj is the original duration of task j and Xj is the expedited duration time for task , then quality, measured on a scale of 0–100 (with 100 being the best), can be represented by the function 100 − min [100,(tj − xj)^2.2] This is only the quality for a task. It is unclear how one might quantify the quality of the project.  How are you measuring system quality, and how does your recommendation measure up relative to that objective?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Task No.  Task Name   Task Duration(Days)  Immediate Predecessor task
1 Preliminary system description  40  —
2 Develop specifications 100  1
3 Client approval 50  2
4 Develop input-output summary 60 2
5 Develop alarm list  40  4
6 Develop log formats  40 3, 5
7 Software definition 35  3
8 Hardware requirements 35  3
9 Finalize input-output summary 60  5, 6
10 Analysis performance calculations  70  9
11  Automatic turbine startup analysis 65  9
12 Boiler guides analysis 30  9
13  Fabricate and ship 200 10, 11, 12
14 Software preparation  80  7, 10, 11
15  Install and check 130  13, 14
16 Termination and wiring lists  30  9
17 Schematic wiring lists 60  16
18  Pulling terminals and cables  60  15, 17
19 Operational test  125  18
20 First firing  19

 

Therefore, Critical Path = 1-2-4-5-6-9-10-13-15-18-19-20

Note: tj is the original duration of task j; dj is the minimum duration of task j.

Expediting Costs ($1,000) and Limits

Task no.            current tj  min dj cost to decrease  tj by X days
2                                                   100       70    1.5x^1.8
6                                                        40       20  2x^2.0
7                                                          35   20   1.x^2.0
10                                                 70       40      1.8x^1.9

14                                             

80     60  1.9x^1.6

15                                                

130   120      0.95x^2.7

19                                               

  125       80   0.9x^2.9

Expediting tasks can be profitable and necessary to meet deadlines, although employees do not really like it. Task completion quality is a function of the task completion time, and we would like to have a high quality. This may conflict with our objective of maximizing profit. Because quality affects future revenues, it is difficult to estimate the dollar impact of poor quality. If  tj is the original duration of task j and Xj is the expedited duration time for task , then quality, measured on a scale of 0–100 (with 100 being the best), can be represented by the function 100 − min [100,(tj − xj)^2.2] This is only the quality for a task. It is unclear how one might quantify the quality of the project. 

  • How are you measuring system quality, and how does your recommendation measure up relative to that objective?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.