RIBNA has estimated 200 m³ concrete and 800 dowels to complete a concrete paving project. 60 work hours is estimated to make dowel baskets and anchor them to the base course. A slipform paver, in 40 work hours, spreads, consolidates, and finishes the concrete slab. On a study date, 600 dowels in 45 work hours and 120 m³ concrete in 30 work hours are used. Based on the above scenario, select the right answer. O The project precent complete (PPC) is 69.00% O The CPIs for the dowel work and the concrete work are 0.8 and 1.0 respectively. O The concrete paving project will be completed 10 hours earlier than its total estimated time O None of the given statements is correct

Linear Algebra: A Modern Introduction
4th Edition
ISBN:9781285463247
Author:David Poole
Publisher:David Poole
Chapter2: Systems Of Linear Equations
Section2.4: Applications
Problem 26EQ
icon
Related questions
Question

Qd 134.

RIBNA has estimated 200 m³ concrete and 800
dowels to complete a concrete paving project. 60
work hours is estimated to make dowel baskets
and anchor them to the base course. A slipform
paver, in 40 work hours, spreads, consolidates,
and finishes the concrete slab. On a study date,
600 dowels in 45 work hours and 120 m³ concrete
in 30 work hours are used.
Based on the above scenario, select the right
answer.
O The project precent complete (PPC) is
69.00%
O The CPIs for the dowel work and the concrete
work are 0.8 and 1.0 respectively.
O The concrete paving project will be
completed 10 hours earlier than its total
estimated time
O None of the given statements is correct
Transcribed Image Text:RIBNA has estimated 200 m³ concrete and 800 dowels to complete a concrete paving project. 60 work hours is estimated to make dowel baskets and anchor them to the base course. A slipform paver, in 40 work hours, spreads, consolidates, and finishes the concrete slab. On a study date, 600 dowels in 45 work hours and 120 m³ concrete in 30 work hours are used. Based on the above scenario, select the right answer. O The project precent complete (PPC) is 69.00% O The CPIs for the dowel work and the concrete work are 0.8 and 1.0 respectively. O The concrete paving project will be completed 10 hours earlier than its total estimated time O None of the given statements is correct
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
Recommended textbooks for you
Linear Algebra: A Modern Introduction
Linear Algebra: A Modern Introduction
Algebra
ISBN:
9781285463247
Author:
David Poole
Publisher:
Cengage Learning
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell
Mathematics For Machine Technology
Mathematics For Machine Technology
Advanced Math
ISBN:
9781337798310
Author:
Peterson, John.
Publisher:
Cengage Learning,