Richard Dulski's firm is about to bid on a new radar system. Although the product uses new technology, Dulski believes that a learning rate of 90% is appropriate. The first unit is expected to take 780 hours, and the contract is for 14 units.
a) The total amount of hours to build the 14 units =
hours (round your response to the nearest whole number).
Expert Solution

This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 1 images

Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- It takes Boeing 27,400 hours to produce the eighth 787 jet. The learning factor is 75%. Time required for the production of the twelfth 787: hours 12th unit time (round your response to the nearest whole number).arrow_forwardKelly-Lambing, Inc., a builder of government contracted small ships, has a steady work force of 10 very skilled craftspeople. These workers can supply 2,440 labor-hours each per year. Kelly-Lambing is about to undertake a new contract, building a new style of boat. The first boat is expected to take 6,100 hours to complete. The firm thinks that 75% is the expected learning rate. What is the firm's "capacity" to make these boats-that is, how many units can the firm make in 1 year? If the operations manager can increase the learning rate to 70% instead of 75%, how many units can the firm make? (Round all numerical responses in this exercise to the nearest whole number.) Total time available = 24400 hours. Number of Boats 4 5 6 8 Total Time 75% Learning Rate 17971 21099 23999 26719 29292 a) Number of boats completed with 75% learning rate = 6. Total Time 70% Learning Rate 16824 19489 21915 24156 26248 b) Number of boats completed with 70% learning rate=arrow_forwardAlthough the learning curve never completely levels off to a horizontal line, if work standards are to be developed, there must be a point at which, for all practical purposes, learning is said to be have stoppped. If we have an 80 percent learning curve and say that the learning effect will be masked by other variables when the improvement in successive units is less than 0.5 percent, at about what unit number can the standard be set?arrow_forward
- Name or state three elements that can unsettle or disrupt the learning curve ?arrow_forward← Kelly-Lambing, Inc., a builder of government contracted small ships, has a steady work force of 10 very skilled craftspeople. These workers can supply 2,440 labor-hours each per year. Kelly-Lambing is about to undertake a new contract, building a new style of boat. The first boat is expected to take 6,100 hours to complete. The firm thinks that 75% is the expected learning rate. What is the firm's "capacity" to make these boats-that is, how many units can the firm make in 1 year? If the operations manager can increase the learning rate to 70% instead of 75%, how many units can the firm make? (Round all numerical responses in this exercise to the nearest whole number.) Total time available = 24400 hours. Number of Boats 4 5 6 7 8 Total Time 75% Learning Rate 17971 21099 23999 26719 29292 a) Number of boats completed with 75% learning rate = Total Time 70% Learning Rate 16824 19489 21915 24156 26248arrow_forward29 ABC Hospital completed its first transplant, and the procedure took 50 hours. The hospital has five more transplants scheduled. Based on other similar procedures carried out, the hospital estimates that it has an 85% learning rate. Estimate the time it will take to complete the third transplant. a 34.5 hours b 36 hours c 38.67 hours d 40 hoursarrow_forward
- In Tronys Inc the first unit takes around 57 hours for the production whereas the learning curve rate is 71%, calculate the time taken by 32nd unit with using crawford model ?arrow_forwardPlease do not give solution in image formate thanku.arrow_forwardA new product made from recycled bio-plastics needs 20 labor hours to complete the build for the first unit. If production operates at a 85% learning curve rate, calculate the average labor hours required per unit to produce five units.arrow_forward
- A new training program at Arid Industries is intended to lower the learning-curve coefficient of a certain molding operation that currently costs $95.50/hour. The current coefficient is .87, and the program hopes to lower the coefficient by 10%. Assume that the time to mold the first product is 8 hours. If the program is successful, what cost savings will be realized when the 2000th piece is produced?arrow_forwardA newly established electric car company estimates that the manufacturing time for their 4th car to be 77.0 hours. Given an 85.0 learning percentage and a labor/overhead cost of $650 per hour, what's the total labor/overhead cost for the first set of 10 cars of the runarrow_forwardGirish Shambu and Delores Reisel are teammates at a discount store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 75%. They forgot to time their effort on the first bike, but spent 5 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be (was) required for: a) The 1st unit= hours (round your response to two decimal places). b) The 8th unit-hours (round your response to two decimal places). c) The total amount of hours to build the 8 units-hours (round your response to two decimal places).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.

Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,

Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education

Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education


Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning

Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.