Station Cut End Area (ft2) 10+00 240 11+00 362 12+00 443 13+00 406 14+00 261 15+00 101 For the data tabulated above, calculate the volume of excavation between stations 10+00 and 15+00. Express your answer in cubic yards to five significant figures.
Station Cut End Area (ft2) 10+00 240 11+00 362 12+00 443 13+00 406 14+00 261 15+00 101 For the data tabulated above, calculate the volume of excavation between stations 10+00 and 15+00. Express your answer in cubic yards to five significant figures.
Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter4: Measuring Site Work, Excavation, And Piling
Section: Chapter Questions
Problem 8RQ
Related questions
Question
Station | Cut End Area (ft2) |
|
10+00 | 240 | |
11+00 |
|
|
12+00 |
|
|
13+00 |
|
|
14+00 |
|
|
15+00 |
|
For the data tabulated above, calculate the volume of excavation between stations 10+00 and 15+00.
Express your answer in cubic yards to five significant figures.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 2 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,