Station Cut End Area (ft2) 10+00 240 11+00 362 12+00 443 13+00 406 14+00 261 15+00 101 For the data tabulated above, calculate the volume of excavation between stations 10+00 and 15+00. Express your answer in cubic yards to five significant figures.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter4: Measuring Site Work, Excavation, And Piling
Section: Chapter Questions
Problem 8RQ
icon
Related questions
Question
Station Cut End Area
(ft2)
10+00 240
11+00
362
12+00
443
13+00
406
14+00
261
15+00
101
For the data tabulated above, calculate the volume of excavation between stations 10+00 and 15+00.
Express your answer in cubic yards to five significant figures.
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Measuring sitework, excavation and piling
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,