The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek: Performance Time Task (seconds) Predecessors 24 B 28 14 15 В. С D. E 12 30 This exercise only contains parts b, c, d, e, and f. ) Given the demand, the cycle time for the production of the new train set = 32.0 seconds (round your response to one decimal place). :) The theoretical minimum number of workstations = 4 (round your response up to the next whole number). ) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Task Workstation # A Station 1 B Station 2 Station 3 Station 3

Microeconomic Theory
12th Edition
ISBN:9781337517942
Author:NICHOLSON
Publisher:NICHOLSON
Chapter10: Cost Functions
Section: Chapter Questions
Problem 10.11P
icon
Related questions
Question

Can you assist me with this question17  by showing me the process step by step so, I  can use this to compare with my notes. I attempted this question numerous times however, Im still having trouble understanding. Thank you. 

The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek:
Performance Time
(seconds)
Task
Predecessors
A
24
B
28
A
14
A
D
15
A
В. С
D. E
E
12
30
This exercise only contains parts b. c. d, e, and f.
o) Given the demand, the cycle time for the production of the new train set = 32.0 seconds (round your response to one decimal place).
c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number).
d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.)
Task
Workstation #
A
Station 1
В
Station 2
Station 3
D
Station 3
Station 4
Transcribed Image Text:The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,500 units per 40-hour workweek: Performance Time (seconds) Task Predecessors A 24 B 28 A 14 A D 15 A В. С D. E E 12 30 This exercise only contains parts b. c. d, e, and f. o) Given the demand, the cycle time for the production of the new train set = 32.0 seconds (round your response to one decimal place). c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number). d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Task Workstation # A Station 1 В Station 2 Station 3 D Station 3 Station 4
Were you able to assign all the tasks to the theoretical minimum number of workstations? No
e) The total idle time per cycle for the process = 27 seconds (enter your response as a whole number).
f) The efficiency of the assembly line with 5 workstations = 82.0% (enter your response as a percentage rounded to one decimal place).
If one used
workstations instead of 5, the efficiency of the assembly line would be = 68.3 % (enter your response as a percentage rounded to one decimal place).
Heln me solve this
Video
Get more help.
Similar questio
Transcribed Image Text:Were you able to assign all the tasks to the theoretical minimum number of workstations? No e) The total idle time per cycle for the process = 27 seconds (enter your response as a whole number). f) The efficiency of the assembly line with 5 workstations = 82.0% (enter your response as a percentage rounded to one decimal place). If one used workstations instead of 5, the efficiency of the assembly line would be = 68.3 % (enter your response as a percentage rounded to one decimal place). Heln me solve this Video Get more help. Similar questio
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Correlation Coefficient
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Microeconomic Theory
Microeconomic Theory
Economics
ISBN:
9781337517942
Author:
NICHOLSON
Publisher:
Cengage
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning