The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Week Item 1 S Gross req 0 Order release 0 NOO 2 3 4 5 6 7 Lead Time (weeks) 0 0 0 0 0 80 0 0 이 0 60 0 2 Level The product structure. The time-phased product structure. 0 T(1) 1 S U(1) 2 V (1) W(1) X (1) Y (2) Z (2) ☑ Y W ☑ N T S U ☑ 2 3 4 5 6 7 Time in weeks

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T
requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm
manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks
to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z.
Click the icon to view the product structure and the time-phased product structure.
In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are
needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to
reflect this change (type 0 if the input box is not used).
Week
Item
1
S
Gross req
0
Order release
0
NOO
2
3
4
5
6
7
Lead Time
(weeks)
0
0
0
0
0
80
0
0
이
0
60
0
2
Transcribed Image Text:The demand for subassembly S is 80 units in week 7. Each unit of S requires 1 unit of T and 1 unit of U. Each unit of T requires 1 unit of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 1 week to make V, 3 weeks to make W, 2 weeks to make X, 2 weeks to make Y, and 2 weeks to make Z. Click the icon to view the product structure and the time-phased product structure. In addition to 80 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the gross material requirements plan to reflect this change (type 0 if the input box is not used). Week Item 1 S Gross req 0 Order release 0 NOO 2 3 4 5 6 7 Lead Time (weeks) 0 0 0 0 0 80 0 0 이 0 60 0 2
Level
The product structure.
The time-phased product structure.
0
T(1)
1
S
U(1)
2 V (1) W(1) X (1) Y (2) Z (2)
☑
Y
W
☑
N
T
S
U
☑
2 3 4 5
6
7
Time in weeks
Transcribed Image Text:Level The product structure. The time-phased product structure. 0 T(1) 1 S U(1) 2 V (1) W(1) X (1) Y (2) Z (2) ☑ Y W ☑ N T S U ☑ 2 3 4 5 6 7 Time in weeks
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,