The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 33 periods? ID Description A B C D E F G LL H Pilot production Select channels of distribution Develop program Test market Patent Full production Ad promotion Release 90% 89% 88% 91% Predecessor None None None A A D C B,E,F,G te 6 7 4 4 10 16 3 2 Variance [(b-a)/6]2 3 4 2 2 5 10 2 1

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question
5
d
The expected times and variances for the project activities are given below, critical
path is A-D-F-H. What is the probability of the completing the project in 33 periods?
ID Description
A
B
Pilot production
Select channels of
distribution
Develop program
Test market
C
D
E Patent
F
G
H
Full production
Ad promotion
Release
90%
89%
88%
091%
Predecessor
None
None
None
A
A
D
C
B,E,F,G
te
6
7
4
st
4
10
16
3
2
Variance
[(b-a)/6]2
3
4
2
2
5
10
2
1
Transcribed Image Text:d The expected times and variances for the project activities are given below, critical path is A-D-F-H. What is the probability of the completing the project in 33 periods? ID Description A B Pilot production Select channels of distribution Develop program Test market C D E Patent F G H Full production Ad promotion Release 90% 89% 88% 091% Predecessor None None None A A D C B,E,F,G te 6 7 4 st 4 10 16 3 2 Variance [(b-a)/6]2 3 4 2 2 5 10 2 1
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Project Management Techniques
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY