The following annual data are from a 160 MW steam turbine-generator plant. Gross generation is 780,000 MWH, net generation is 723,000 MWH, operating hours is 7,730, average load is 99.67 MW, and maximum peak load is 160 MW. Determine the load factor
The following annual data are from a 160 MW steam turbine-generator plant. Gross generation is 780,000 MWH, net generation is 723,000 MWH, operating hours is 7,730, average load is 99.67 MW, and maximum peak load is 160 MW. Determine the load factor
Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter2: Fundamentals
Section: Chapter Questions
Problem 2.28MCQ: The total instantaneous power delivered by a three-phase generator under balanced operating...
Related questions
Question
The following annual data are from a 160 MW steam turbine-generator plant. Gross
generation is 780,000 MWH, net generation is 723,000 MWH, operating hours is
7,730, average load is 99.67 MW, and maximum peak load is 160 MW. Determine
the load factor
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning