The project will take The critical path is The late start on Activity C is The slack on Activity Cis The slack on Activity Dis The early start on Activity E is days. days. days. days. days.
Q: Kelson Sporting Equipment, Inc., makes two different types of baseball gloves: a regular model and a…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: Design a Gantt chart using the following data, removing blank spaces on the chart. TASK ASSIGN…
A: Gantt charts can be created manually using pen and paper, but they are most commonly created using…
Q: The Faculty of Science at UPOS had procured a suite of thirty (30) Smart Digital Lockers and were in…
A: A requirements engineering technique called the Volere model was first presented in 1995. It's…
Q: State one retail business and talk about how their operational level management and inventory system…
A: Inventory management involves managing a company's inventory of raw materials, work-in-progress, and…
Q: What do we mean by the term queue discipline? o Queue discipline refers to how people should behave…
A: A queueing model is a mathematical framework used to analyze and understand how entities (such as…
Q: Whether businesses like it or not, bloggers have tremendous power. A positive review on a popular…
A: The ascent of social media and online platforms has led to another type of influencer - bloggers.…
Q: examine the term settlement in the context of industrial relation
A: Below is the explanation of the term settlement in the context of industrial relation:
Q: Your company currently keeps a safety stock of 554 units of a particular product that has a lead…
A: Find the given details below: Given details: Weeks Demand 1 1176 2 955 3 780 4 1052 5…
Q: Procurement is just like plants and animals, it's born, it grows, it matures and eventually dies'.…
A: The statement "Procurement is just like plants and animals, it's born, it grows, it matures, and…
Q: Lego problem is to use small and big Lego bricks to build up tables and chairs. Each produced table…
A: Let the number of chairs be x. Let the number of tables be y.
Q: What are some of the challenges that a corporation would have to overcome in order to achieve the…
A: A successful company plan cannot exist without a similarly effective brand strategy. When executed…
Q: Which of the following represent(s) strategic challenges of competing in a new industry? O A firm…
A: Strategic management is the process of planning, implementing, and evaluating an organization's…
Q: What is the best approach to evaluating an ERP system, regardless of the type?
A: Enterprise resource planning systems centralize data from across an organization into a unified…
Q: The sale data is shown as follows: Month 1: 11 Month 2: 52 Month 3: 95 Using Weighted…
A: The weighted Simple moving average is determined with the following formula WSMA =…
Q: A fabrication cell at Spradley's Sprockets uses the pull method to supply gears to an assembly line.…
A: Requirement (D) = 547 Containers = 0.3 One containers = 1.3 Lead time (L) = 0.3+1.3 = 1.6 Size of…
Q: Provide a online a reaction paper comparing two different firms as to how they adopt training…
A: Training is the process of teaching and developing the skills, knowledge, and abilities of employees…
Q: These actions were considered to be important if they were to reduce the overall cost and stay ahead…
A: CASE SUMMARY- Juan Hernandez, the head buyer of Connery Manufacturing Company, was elevated to the…
Q: The annual demand for an item is 10,000 units. The cost to process an order is $75 and the annual…
A: Given, Annual demand D = 10000 units Order cost S = $75 Holding cost = 20% of the price Price P is…
Q: Choose two research articles on the ethics of project management and describe their findings.
A: Below are the two research articles on the ethics of project management and their findings:
Q: Is the workflow management system targeting a specific area of concern
A: A workflow management system can be defined as a software device that helps organizations manage and…
Q: You have determined that a 75 percent learning curve is appropriate to produce an item, and the…
A: Formulae used: For learning curve- Tn = T1 x nb Where, Tn = Time for the nth unitT1 = Time for the…
Q: The phrase "full-service provider" may mean several things depending on the context. What benefits…
A: A growing number of organisations have adopted the idea of becoming a one-stop shop in recent years.…
Q: Scenario: A group of University students are considering opening a new business in the Tourism…
A: A sustainable competitive advantage can bed defined as the special advantage that a company has over…
Q: 12) The grouping of the offices by functional area is an example of a(n) A) good B) service C) input…
A: Strategic planning is a process to develop a plan of action to achieve them. It involves analyzing…
Q: Following is the payoff table for the Pittsburgh Development Corporation (PDC) Condominium Project.…
A: Given - Probability of strong demand (S1)= 0.78Probability of weak demand (S2)= 0.22Expected Value =…
Q: How would the negotiation of the distribution contract with Riscola benefit a company like Riham?…
A: Negotiation is the process of discussing and reaching an agreement between two or more parties who…
Q: A maintenance building construction project also includes an external electrical generator and water…
A: Find the information below:
Q: Craft a high-level Procurement Management Plan for the project. Craft a high-level Human Resource…
A: A procurement management plan is a written document that defines the methods and tactics for…
Q: Kindly prepare five (5) SMART objectives for the post of Court Administrator - Administratively,…
A: SMART objectives are objectives that are Specific, Measurable, Achievable, Relevant, and Time-bound.…
Q: Given is a decision payoff table. Alternatives Small Facility Medium Facility Large Facility Low 26…
A: Given-
Q: General project information: project name, sponsor, project team • Problem/opportunity statement:…
A: NOTE: We are allowed to do the first three sub-parts only. Effective project management requires a…
Q: 9. Sony, a television company, has three major departments for the manufacture of its two models, A…
A: Decision Variables: Suppose-X1 be the no. of model A to be producedX2 be the no. of model B to be…
Q: Can you see any common blunders made in Performance Testing?
A: Project management is the process in which a project is managed, organized, controlled, and…
Q: a) Draw an arrow diagram representing the project. b) Find the total float for each activity. c)…
A: A network diagram shows the sequence of the task that is done to complete a project. It usually…
Q: Explain the relationship between customer expectations and customer perceptions
A: Customer expectations and customer perceptions closely related and can have significant impact on a…
Q: A. What is capacity?
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: Topic: Managment Information system Please read and answer the different parts operational…
A: Below are the answers for the discussion given:
Q: Just what is performance testing, and where do the bottlenecks lie?
A: Below is the definition of performance testing and its bottlenecks:
Q: How effective is it to submit vendor invoices only?
A: Overseeing tasks effectively working is tied in with being coordinated, productive, & proactive.…
Q: With reference to the case study provided, critically evaluate each potential location, and suggest…
A: Location strategy is a critical decision-making process that involves identifying and selecting the…
Q: Need assistance in the procurement plan question based on the senario FAO-Funded Aquaponics…
A: A Procurement Management Plan can be defined as the formal record that frames the processes and…
Q: Use weighted average and the past four week's demand to predict next week demand. Demands for the…
A: Simple average is calculate with following method Simple average = Total demandN
Q: While doing performance testing, what do you think to be the most significant elements to take into…
A: Performance testing is a type of software testing that evaluates the system's performance under a…
Q: The MGMT Insurance Ltd. accepts payments on various insurance policies from employees of businesses…
A: Below are the two findings about the analysis:
Q: Scenario -- Diamond Business Offices The following information was gained from an interview with the…
A: To ensure that all stakeholders receive the right level of communication during the project, the…
Q: Using the below table calculate critical path for the project. Which tasks are on the critical path?
A: Critical and non-critical activities refer to the tasks or activities involved in a project, and…
Q: Of 3000 employees at a given company, 175 experienced an injury while on the job in a given week. Of…
A: To calculate the total person-time of observation, we need to multiply the number of employees by…
Q: As a distributed team, it is important for us to all get together in person throughout the year. We…
A: The issue is setting up the necessary arrangements for a scattered team's staff meeting. Distributed…
Q: 3.5. The Great North Woods Clothing Company is a mail-order company that processes thousands of mail…
A: Formulae used: c̅ = Total number of defectsNo. of samples =Σck Upper control limit (UCL) = c +…
Q: The following information was gained from an interview with the Managing Director (MD) of Diamond…
A: In an interview, the Managing Director (MD) of Diamond Business Offices, a provider of comprehensive…
Rr.6.
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 2 images
- Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 4 800 2 1300 B - 10 1200 7 2400 C A 6 1100 4 1700 D A,B 7 1000 4 1600 E C 10 2000 8 3000 F C,D 5 900 - - (a) Draw the network and find the critical path duration of the project, total cost of project using normal times. (b) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below. (Note: Activity “F” cannot be crashed) Activity Maximum Time Reduction (day) Cost to Crash per Period ($/day) A B C D E F (c) Find the optimal way of getting a 20-day delivery time. What is the project cost? (d) Find the optimal way of getting a 18-day delivery time. What is the project cost?I need a detailed explanation and assistance to solve the this problem: A company decides to plan a project, with activities, precedences and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F a) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration. b) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s). C) Draw a Gantt chart of the schedule, based on earliest starting times d) Which activities must be completed by day 60 to ensure that the project is not delayed?The following estimates of activity times (in days) are available for a small project: Activity Optimistic Most Probable Pessimistic A 4 5.0 6 B 8 9.0 10 C 7 7.5 11 D 7 9.0 10 E 6 7.0 9 F 5 6.0 7 Compute the expected activity completion times and the variance for each activity. An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path.
- Consider the following data (ETB and days). Draw activity network of the project. Crash the activities step by step until all paths are critical. Activity Normal Time Normal Cost Crash Time Crash Cost 1-2 20 600 17 720 1-3 25 200 25 200 2-3 10 300 8 440 2-4 12 400 6 700 3-4 5 300 2 420 4-5 10 300 5 600 4-6 5 600 3 900 5-7 10 500 5 800 6-7 8 400 3 700The following table describes project XYZ Duration Predecessor Variance A 5 2 B 3 A 1 C 13 A 6 D 18 B 2 E 10 B 4 F 4 D, E 1 G 11 C, E 5 H 9 F, G 2 I 2 H 1 Based on the information provided, perform the following tasks: Identify the crucial path and project duration Calculate probability that the project in going to be completed after the day 45Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project: A. Draw a project network. B. What are the critical activities and what is the expected project completion time? C. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?
- A group of developers is building a new shopping center. A consultant for the developers has developedthe following table of activities, durations and predecessors. Determine the earliest start times andfinish times, latest start and finish times, activity slack, critical path and duration for the project. Thereis a Bonus for finishing the project at 90% of the projected date. The bonus for early completion is$50,000. Which activities should be crashed, if the cost for 1 week reduction, for any activity, is $3500per week, and what is the total cost of crashing? And, Net Bonus, if any.You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…The following estimates of activity times (in days) are available for a small project: Activity Optimistic Most Probable Pessimistic A 4 5.0 6 B 8 9.0 10 C 7 7.5 11 D 7 9.0 10 E 6 7.0 9 F 5 6.0 7 An analyst determined that the critical path consists of activities B-D-F. Compute the expected project completion time and the variance of this path. What is the probability the project will be completed in 25 days?
- Please assist in detailed explanation on the following question in Project Scheduling: 1) - A company decides to plan a project, with activities, precedence and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F Questions: 1.1) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration. 1.2) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s). 1.3) Draw a Gantt chart of the schedule, based on earliest starting times 1.4) Which activities must be completed by day 60 to ensure that the project is not delayed?2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded By Regular Crash Regular Crash A -- 6 days 2 day $2000 $3800 B -- 12 6 2000 10000 C A 4 2 1000 4000 D B, C 10 6 3400 4600 E D 8 6 2800 3900 F E 6 2 5000 7600 G B, C 18 8 16000 19600 H F, G 6 4 2000 4000 (a) Construct a network including the Early and Late Start and Finish times. (b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?The estimated times and immediate predecessorsfor the activities in a project at George Kyparis’s retinal scan-ning company are given in the following table. Assume thatthe activity times are independent. a) Calculate the expected time and variance for each activity.b) What is the expected completion time of the critical path?What is the expected completion time of the other path inthe network?c) What is the variance of the critical path? What is the vari-ance of the other path in the network?d) If the time to complete path A–C is normally distributed,what is the probability that this path will be finished in22 weeks or less?e) If the time to complete path B–D is normally distributed,what is the probability that this path will be finished in22 weeks or less?f) Explain why the probability that the critical path will befinished in 22 weeks or less is not necessarily the probabil-ity that the project will be finished in 22 weeks or less.