Using the below table calculate critical path for the project. Which tasks are on the critical path?
Q: Q2: Textile Manufacturing Problem The Great Threads Company is capable of manufacturing shirts,…
A: Decision Variables: Suppose-X1 be the no. of shirts produced each weekX2 be the no. of shorts…
Q: Explain the process of Project Benefit Realization. Describe the five (5) fundamental broad…
A: Project Benefit Realization is the process of identifying, measuring, and tracking the benefits that…
Q: THE TOPIC IS Research proposal about digital divide in Malaysia The Literature Review should be 3…
A: Like most non-industrial countries, Malaysia has forever been worried about bringing its huge…
Q: Compute MAD for each set of forecasts. Given your results, which forecast appears to be more…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: The amount of problems that are discovered in a piece of software before it is made available to…
A: Product development is the process of creating or improving a product from concept to market. It…
Q: what is called when pharmaceutical companies tilt their research toward areas of opportunities for…
A: The pharmaceutical industry is an exceptionally profitable and serious area that puts vigorously in…
Q: Activity Immediate Predecessors tn (weeks) cn tc (weeks) cc A --- 5 $500 3 $900 B A 6…
A: Given data-
Q: Magnus Packard is an underwriter who works at Capital State Financial where he processes loans…
A: SPT or Shortest processing rule is a sequancing model based on the processing time. Here it consider…
Q: (c) Based only on the critical path, what is the estimated probability the project can be completed…
A: Note: since you posted multiple questions, we will provide the solution only to the first question.…
Q: What is the critical path?
A: The critical path is a crucial concept in project management that refers to the sequence of…
Q: what is the probability that the project will take less than 42 weeks ?
A: Here, as per the question, I would determine the Probability value, here, first, I would determine…
Q: Discuss the factors that need to be taken into account when making packaging decisions, promotional…
A: The choice of packaging characteristics is influenced by a variety of variables, including size,…
Q: Find the optimal solution by simplex me
A: Let the number of the self-propelled models be x. Let the number of the push-type mower be y.
Q: Alex is facing the difficult task of considering revamping the compensation system. Currently what…
A: The compensation system includes total rewards which are given to the employee of an organization. A…
Q: How may formative scales be used to investigate the effects of cross-level moderation?
A: Formative scales are a type of measurement model used in research to measure a construct by…
Q: Create a PERT NETWORK and provide a critical path
A: PERT stands for Program Evaluation and Review Technique, and it is a project management tool used to…
Q: Describe the impact that a large number of continuously operating processes has on the capacity…
A: The capacity analysis is the process of evaluating a system's ability to produce goods or services…
Q: what are the role of these stakeholders Human Resource (HR) Manager Project Manager (PM) Software…
A: A software company has created a client-specific order processing system in a hypothetical…
Q: How important are intranets, extranets, and the internet in today's workplaces for the purposes of…
A: In today's workplaces, intranets, extranets, and the internet play a critical role in supporting…
Q: Mabry Company: Transportation Method -- Backorders Permitted Period of Production Beginning…
A: Find the calculations formulas below:
Q: What opportunities exist for enhancing operations via the use of information technologies in the…
A: Operations management is the process of planning, organizing, and controlling the activities that…
Q: Write a one-page APA formatted paper that answers the reflection question, "What do I value most as…
A: Professional values are fundamental for guiding people in deciding and accomplishing objectives in…
Q: Problem 11-17 (Static) The National State Bank is trying to make sure that they have enough tellers…
A: Given- Minutes Available = 1 hour = 60 minutesService time = 5 minutes/customerNo. of counter = 8…
Q: If demand is expected to increase to 84 customers
A: The average number of customers per day = 70 Utilization rate = 65% The expected increase in demand…
Q: ERP systems often conform to standard procedures. Whose standards, therefore, are the right ones?…
A: ERP systems are designed to streamline and standardize business processes across an organization,…
Q: 4. Various measures of cost Suppose the imaginary company of Roobek is a small, Reno-based American…
A: Formulas used-Marginal cost of unit Q+1= Total cost of unit Q - Total cost of unit Q-1Fixed cost…
Q: Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be…
A: Given:
Q: Part 1: Introduce yourself by identifying your Management level and your functional area. For your…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: The flash floods in Kamwala South have taken their toll on the residents of the area. For many, the…
A: The recent flash floods in Kamwala South have disrupted and seriously damaged the livelihoods of the…
Q: Community Needs Assessment Assignment Mother and Infants Scenario You are the corporate wellness…
A: Below are two potential nutrition/health-related barriers or problems that females in this…
Q: 1. The network 2. The CP and expected completion time 3. All expected activity times, variances and…
A: NOTE: We are allowed to do the first three sub-parts only. The Critical Path Method (CPM) is a…
Q: Using the following table, calculate the slack for Task H
A: In the context of the Critical Path Method (CPM), "slack" refers to the amount of time that an…
Q: When manager make a decision to open a new branch of Haidilao hot pot restaurant (海底攒) inMacau,…
A: When manager make a decision to open a new branch of Haidilao hot pot restaurant in Macau, he/she is…
Q: (a) Find the shadow price for Resource 2. (Round your answer to the nearest cent.) $ (b) Identify…
A: The greatest price that should be paid to get an additional unit of resource is typically described…
Q: How can a company ensure ethical and sustainable practices in its global supply chain, particularly…
A: Sustainable supply chain management is defined as the management of material, information and…
Q: Use the decreasing time algorithm to create a priority list for the digraph below, then schedule the…
A: Based on the given digraph we have to first find the critical time for each vertex.Critical Time for…
Q: 2. Solve this model using graphical and simplex method and compare the answers. A transistor radio…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: If Toyota Motor Company receives an order on May 4, begins production on May 17, and ships the order…
A: Date of order recieve = 4th May Begin production = 17th May Order ship = May 19
Q: Topic: Managment Information system Please read and answer the different parts operational…
A: Below are the answers for the discussion given:
Q: how does toyota apply innovation in the development of operation management techniques.
A: Operations management techniques can be defined as the techniques and methodologies used to plan,…
Q: Use this sensitivity report to answer the questions below. What constraints are binding (at that…
A: Based on the Given Sensitivity Report: Shadow Price of High-Grade Constraint = 10 Shadow Price of…
Q: Outline a risk management approach to quality issues.
A: Risk management in quality can be defined as the most common way of identifying and moderating…
Q: Define the terms main product, joint product, and byproduct. Give at least one example of each type…
A: Main Product: A main product is a product that is the primary focus of a production process, and it…
Q: The coefficient of variation for inter-arrival times of customers arriving at a sandwich shop is…
A: Given that, inter-arrival times of customers arriving at a sandwich shop is equal to 3.
Q: The members want to know how many of each item they should bake to maximize the money they make.
A: It is believed that the invention of linear programming was a major step forward for mankind since…
Q: You may need to use the appropriate technology to answer this question. Mueller & Associates is a…
A: Formulae used: For Expected Time- Te=(O+4M+P)6 For Variance- Variance =P-O62 Where:O=Optimistic…
Q: The probability that the seminar will be ready in time is 0.8643 (Enter your response rounded to…
A: A network diagram shows the sequence of the task that is done to complete a project. It usually…
Q: Solve the following LP (noting that x2 is urs) x2 being urs reflects that the business can must…
A: Given- Maximize z =30x1-4x2 Constraints: Subject to- 5x1≤30+x2 x1≤5 x1≥0; x2 urs
Q: Consider the transportation table below. The solution displayed was obtained by performing some…
A: The transportation method is a linear programming technique used in operations management to…
Q: Problem 11-6 (Static) Avis Company is a car rental company that is located three miles from the Los…
A: Formulae used: According to Little’s Law: Inventory=Through put rate × Flow time
Using the below table calculate critical path for the project. Which tasks are on the critical path?
Task | Predecessor | Duration (Weeks) |
A | - |
32 |
B | - | 11 |
C | - | 12 |
D | B,C | 16 |
E | A,B | 23 |
F | A | 23 |
G | D | 22 |
H | D | 33 |
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 1 images
- Using the following table, calculate the project duration Task Predecessor Duration (weeks) A - 1 B A 2 C - 2 D - 3 E B 3 F C, D 4 G E,F 6 H F 1Use the following project status information to calculate each of the requested EVM numbers below (a-i).The project status is reported at the end of week 13. Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 Weeks 100 percent complete $5,000B $8,500 3 Weeks 100 percent complete $9,000C $15,000 4 Weeks 75 percent complete $14,000D $10,000 4 Weeks 50 percent complete $9,000 E $12,000 4 Weeks Not startedF $15,000 5 Weeks Not started a. Planned Valuedb. Actual costc. Cost varianced. Schedule variancee. Cost performance indexf. Schedule performance indexg. Budget at completionh. Estimation to completei. Estimation at completionDraw CPM network of activities tabulated below: 1. Calculate the expected duration and the standard deviation for the critical path. 2. Compute the followings: (a) The probability that the project will finish by the end of day 50 (b) The probability that the project will finish at day 52 (c) The probability that the project will finish before the start of day 49. (d) The completion date with at least a 95% confidence level
- The optimistic duration for a project is 10 weeks. The worst case estimate is 22 weeks, and the most likely duration is 13 weeks. Using 2 sigma estimates and PERT, what is the range of the duration estimate? 12 to 16 weeks 13 to 17 weeks 10 to 18 weeks 11 to 19 weeksA) What is the variance activity B? 2 decimal places B) What is the variance of activity F? 2 decimal places C) what is the probability the project can be completed? 4 decimals places only D) what is the probability the project will be 3 weeks late from the expected completion time ? 4 decimal places only.Using the information given, calculate the expected time foreach of the project activities
- a) Draw an AON diagram of the project, including activity durations. b) Define the critical path, listing all critical activities in chronological order. c) What is the project duration (in weeks)? d) What is the slack (in weeks) associated with any and all noncritical paths through the project?You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…Using the information in Table-1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Task Description Duration (WorkingDays) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware Installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I Handover and Go-Live 5 H (i) Determine the critical path of the project (ii) Calculate the planned duration of the project in weeks (iii) Identify any non-critical tasks and the float (free slack) on each.
- The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the __________ functions. a. schedule and cost b. technical and managerial c. cost and performance d. performance and scheduleYou are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Immediate Predecessor A 4 3 $2,000 $2,100 - B 2 1 $2,200 $2,800 - C 3 3 $500 $500 - D 8 6 $2,300 $2,600 A E 6 3 $900 $1,200 B F 3 2 $3,000 $4,200 C G 4 2 $1,400 $2,000 E, F How long will the project take? What is the total cost to complete the project in normal time? If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased? What is the maximum time that the project can be crashed? How much will the cost increase if it is crashed the maximum?