The table below includes information about four jobs and three work centers. Please use owing priority order, 1, 2, 3, 4 to develop a Gantt chart. What is the makespan? Job Work center 1 A/2, B/1, C/4 C/4, A/2 B/4, A/2 B/4, А/2, C/3 3 4
Q: Explain how technology has influenced scheduling?
A: Scheduling is the process of controlling, managing, and assigning the work to the employees in the…
Q: What general trade-offs are involved in sequencing decisions? In scheduling decisions?
A: The trade-offs associated with sequencing decisions are:
Q: There are following seven jobs and they must pass through Machine 1 and Machine 2. Operating time…
A: Given: Job 1 2 3 4 5 Machine-1 4 16 8 12 3 Machine-2 5 13 7 11 9
Q: Assembly-Line Balancing The time to perform each task and the tasks that must be immediately…
A: Given data is
Q: The following table details the tasks required forIndiana-based Frank Pianki Industries to…
A: Activity Performance Predecessors A 5 B 1.5 C 3 B D 4 C E 3 B F 2 A, E G 3 H…
Q: Exercise 8-37, 8-38, 8-39 & 8-40 (Static) (LO 8-2, 3, 5) Skip to question [The following…
A:
Q: 3. A producer of inkiet printers is planning to add a new line of Rrinters, and xou haxs been asked…
A: Given:
Q: Describe the four step criteria for scheduling ?
A: Scheduling is the process of determining the most efficient way to control and organise any supply…
Q: Given the operation times provided:a. Develop a job sequence that minimizes idle time at the two…
A: The job sequence using Johnson’s rule is: B-A-C-E-F-D.
Q: Shown below are the tasks, times, and precedence requirements for the work required to assemble a…
A: The production line is the set of machines in a systematic manner for assembling of product in an…
Q: 1. Crispy chips company operates in two shifts every day. Each shift is for a duration of 8 hours.…
A: Answer: The total time taken in the process of manufacturing = set up time + Run time…
Q: Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a…
A: Total duration during the day = 480 mins The average daily demand of chairs = 50 Desired output =…
Q: The Carry-on Luggage Company must set up an assembly line for a wheeled carry-on bag. Forecasts show…
A:
Q: Illinois Furniture, Inc., produces all types of officefurniture. The "Executive Secretary" is a…
A: Given- Available operating time = 480 minutes per day Desired output rate = 50 chairs
Q: Given the ta. data shown, prepare the following: a) PERT / CPM Network b) Tabulated CPM Calculations…
A: Below is the solution:-
Q: Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro…
A: Given details: Activity Performance time(min) A 10 B 12 C 8 D 7 E…
Q: The following table details the tasks required for Florida-based James Industries, Inc. to…
A:
Q: A foreman has determined the expected processing times at a machine for a set of jobs and now wants…
A: Note: - Since we can answer only up to three subparts we will answer subpart a-1(1, 2, 3, and 4)…
Q: Using the above data, solve the assembly-line balancing problem and calculate the efficiency of your…
A:
Q: The City Commission of Nashville has decided to build a botanical garden and picnic area in the…
A: Precedence table-
Q: A computer factory in Tangerang plans to increase production line for new products and plan to…
A: Here, This question includes several sub-parts, I have answered the first three sub-parts in the…
Q: Five jobs are ready for processing at time zero through a workstation. The details of the processing…
A: SPT- Shortest Processing Time SPT states the job or customer arriving at the work station has…
Q: 17-13. Jobs processed through Percy's machine shop pass through three operations: milling, grinding,…
A: Given information Job Milling Grinding Turning A 5 1 4 B 2 2 5 C 3 2 1 D 1 3 0 E 4 1…
Q: The desired daily output for an assembly line is 540 units. This assembly line will operate 720…
A: Line balancing is a process which allocate activity to right workstation based on different…
Q: The Sail-Sea is a boat manufacturer. The assembly location is available for production of 60 boats…
A: The precedence diagram based on the given information is as follows:
Q: How are scheduling and productivity related?
A: Productivity: Productivity is the quantity of work completed by a team or an individual.…
Q: Referring to the table below, Jobs Work Center 1 (2 (In Days) Dates in Days) Work Center Due 3 6. 4.…
A: Find the Given details below: Given details: Job Required Days Due Dates WC 1 WC 2 1 3 2 9…
Q: Jack has gathered the following information for Work Center 2, the work center that directly feeds…
A: Given data:
Q: obs Work Center 1 ( in Days ) Work Center 2 ( in Days ) Due Dates 1 6 2 10 2 5 4 12 3 5…
A: Find the Given details below: Given details: Job Required Days Due Dates WC 1 WC 2 1 6 2…
Q: Managers at the First Community Bank are attempting to shorten the time it takes customers with…
A: Bottlenecks are basically the obstacles which can lead to slowing down of the whole process. At the…
Q: Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro…
A: Given information Activity Duration Immediate predecessors A 10 B 12 A C 8 A, B D…
Q: Using the above data, solve the assembly-line balancing problem and calculate the efficiency of your…
A:
Q: Please provide the CPM result for each of the following metrics: E[S_{end}] = E[ES_{D}] =…
A: We are allowed to do first three sub parts only. Please post rest parts again to get answers. The…
Q: Given the following information on job times and due dates, determine the optimal processingsequence…
A: FCFS refers to First Come, First Serve. SPT refers to Shortest Processing Time. EDD refers to the…
Q: a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this…
A: Tasks are assigned to workstations on the basis of total cycle time and minimum number of…
Q: Draw a Pert Diagram based on the following data. Task Duration Hours Predecessor A NONE NONE NONE В…
A: Critical path is a sequence of activities in a project where any delay or deviations in the…
Q: АСTIVITY PREDECESSOR DURATION (days) A1 3 A2 A1 4 АЗ A1 A4 A2 5 A5 АЗ 1 Аб АЗ 2 A7 A4,A5 Аб,А7 4 A8…
A: Find the Given details below: Activity Predecessor Duration(Days) A1 - 3 A2 A1 4 A3 A1 2…
Q: c Golf Cart c golf cart Time on Hand 1 0 10
A: Given: Parts List for Electric Golf Cart Lead Time Quantity on Hand Electric golf cart 1 0…
Q: pls be quick !! The operations manager of an assembly and paint shop has five trucks to schedule…
A: Given Details: Truck Assembly(Hours) Paint(Hours) A 7 10 B 9 3 C 8 7 D 4 4 E 12 5
Q: a Using the data in the table, calculate the expected time (ET) and VAnace uI expected time (ET) Job…
A: THE ANSWER IS AS BELOW:
Q: The Carry-on Luggage Company must set up an assembly line for a wheeled carry-on bag. Forecasts show…
A: Note: Since you have posted a question with multiple subparts, we will solve the first three…
Q: For each of the problems listed, indicate precisely what or who would correspondto jobs and who or…
A: d. While transferring long-distance phone calls from one city to another, the "phone calls" would be…
Q: The normal time for a work cycle in a worker-machine system is 6.0 min. For setting the standard…
A: 1. The machine time per cycle can be calculated as, Tm=6-0.75=5.25 minutes The internal normal…
Q: A manufacturing company is designing an assembly lineto produce its main product. Th e line should…
A: A bottleneck arises in a production system when workloads exceed the capacity of the manufacturing…
Q: Management wants to design an assembly line that will turn out 800 videotapes per day. There will be…
A: Note:-We’ll answer the first three subparts of the question since the exact one wasn’t specified.…
Q: An assembly line is to operate eight hours per day with a desired output of 200 units per day. The…
A: Given-
Q: James Lawson has decided to run for a seat as Congressman from the House of Representatives,…
A: The expected WBS is as follows:
Q: Karina Nieto works for New Products Inc., and one of hermany tasks is assigning new workers to…
A:
Q: The table below define
A:
Q: b. In order of greatest positional weight. Tiebreaker: most following tasks. (Use your rounded cycle…
A: Given- Operating time = 60 minutes Desired Time = 30 units
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Predecessor (S) Time (Days) A - 2 B - 5 C - 1 D B 10 E A;D 3 F C 6 G E;F 8 Which activity has the highest slack timeRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 6 C − 2 D B 10 E A, D 3 F C 5 G E, F 8 Slack time for each of the activities is?Create an AOA diagram based on the information Task A, duration 6, dependent on noneTask B, duration 5, dependent on noneTask C, duration 3, dependent on noneTask D, duration 12, dependent on Task B and Task C Task E, duration 2, dependent on Task ATask F, duration 5, dependent on Task BTask G, duration 1, dependent on Task BTask H, duration 9, dependent on Task E and Task FTask I, duration 7, dependent on Task GTask J, duration 7, dependent on Task HTask K, duration 3, dependent on Task ITask L, duration 5, dependent on Task D
- NB: Answer all the questions within 30 mins Table 1 Activity Predecessor Duration (weeks) A - 5 B A 4 C A 5 D B 6 E C 3 F D, E 4 Use Table 1 to calculate the following: Draw the resultant Gantt chart. Construct the PERT/CPM chart for the tasks as they appear in Table 1.[1] HINT: Do not forget the Start Date and Finish Date for each task. Indicate at minimum three dependent task patterns. Indicate all the multiple successor tasks. Indicate all the multiple predecessor tasks. Show the critical path of this project. Justify why the given critical path is valid.Exercise 8-37, 8-38, 8-39 & 8-40 (Static) (LO 8-2, 3, 5) Skip to question [The following information applies to the questions displayed below.]Pacific Ink had beginning work-in-process inventory of $744,960 on October 1. Of this amount, $304,920 was the cost of direct materials and $440,040 was the cost of conversion. The 48,000 units in the beginning inventory were 30 percent complete with respect to both direct materials and conversion costs. During October, 102,000 units were transferred out and 30,000 remained in ending inventory. The units in ending inventory were 80 percent complete with respect to direct materials and 40 percent complete with respect to conversion costs. Costs incurred during the period amounted to $2,343,600 for direct materials and $3,027,840 for conversion. Exercise 8-37 (Static) Compute Costs per Equivalent Unit: Weighted-Average Method (LO 8-3) Required: a. Compute the equivalent units for the materials and conversion cost calculations. b.…Stan's No Touch Car Wash is looking to implement a new ERP system. Colin Alexander has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. Tasks Predecessors mu_t sigma_t Start 0 0 A start 25 12 B A 17 14.11 C A 45 46.35 D A 32 15.36 E A 37 10.36 F C,D 10 11.8 G B,F 41 15.17 H E,G 44 44.44 end H 0 0 Colin has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: Metric Description E[ES_i] Expected early start time for task i E[EF_i] Expected early finish time for task i E[LS_i] Expected late start time for task i E[LF_i] Expected late finish time for task i Pr(S_i =< t) Probability the start time for task I =< t Pr(F_i =< t) Probability the finish time for task I…
- 3. Review the PERT diagram below, and discuss how you would find the critical path.Instruction:a. Construct AON diagram for the following data.b. Identify critical path.c. Conduct CPM analysis by identifying ES, EF, LS, LF, Slack time to confirm the critical path.Instruction: a. Construct AON diagram for the following data.b. Identify critical path.c. Conduct CPM analysis by identifying ES, EF, LS, LF, Slack time to confirm the critical path.
- Q. Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resource Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. What is the project duration now? Could something like this happen in real projects? Do it in Excel Spreadsheet. Please calculate/draw the network plan with unconstrained resources. Draw the constrained resource loading schedule, then the constrained resource activity schedule (or new constrained network diagram) Explain it in detail.Case Study 5: Project Management – Facility Layouts Samantha’s Appliances has developed a new European-style convection oven that will be made on an assembly line. The schedule requires 80 ovens in an 8-hour day. The assembly includes seven tasks. The table below indicates the performance time and the sequence requirements for each task. Task Performance Time (minutes) Task must follow Task listed below A 1 B 2 A C 3 B D 2 B E 4 C, D F 1 E G 2 F State the purpose of line balancing in an assembly line operation. State the definition of Cycle Time. What is the cycle time for this assembly operation? What is the theoretical minimum number of workstations? Draw the precedence diagram.Q3- Udesign is a plant producing mass production dresses. The following table shows the tasks needed to be preformed, their task times and proceeding tasks. It is required to produce 30 dresses per hour.TaskImmediate predecessorTask time (sec)A-30B-40C-20DA100EB,D25FC,D50GD,E,F50HG90a- Compute the cycle time and minimum number of workstations requiredb- Draw the precedence diagramc- What is the maximum output for this lined- Assign tasks to workstations using most number of followerse- Compute efficiency of such line