Time (weeks) Immediate Time (weeks) Immediate Activity Predecessor(s) Activity Predecessor(s) a a A 4 12 G 3 3 С. Е 1 9 24 A H. 2 F C 8 12 16 5 F D. G. H I, J 5 7 10 A J 6 8 12 3 4 В K 3 3 4 F 6 8 21 С, Е a) The expected (estimated) time for activity C is 12.00 weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.78 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A-B -E -F -H -J - K. d) The estimated time for the critical path is 44.99 weeks. (Round your response to two decimal places.) e) The activity variance along the critical path is 24.00 weeks. (Round your response to two decimal places.) f) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 40 weeks or less is places.) (Enter as a probability and round your response to three decimal
Q: 1. Applied Digital Solutions is expanding its operations to include a new product line for…
A: Activity Immediate Predecessors 1 - 2 - 3 1 4 1 5 1 6 4 7…
Q: Air pollution control activity us going on in the suvera foods which has an expected activity time…
A: The expected time is the time at which the whole project is going to complete successfully.
Q: Q1: For activities shown in table below, find the new time of project after updating, if the project…
A: Given data is
Q: 1- Data for small project are given, determine the following 1- ES for Activity C. E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Activity A B D E F 3 Activity Predecessor 4 B C, D B E 2 None of the above 4 8 How many paths are…
A: In the question, we have the table data, this data includes activity id, the immediate predecessor…
Q: Q1) by using Bar chart planning technique find the following a- Total duration for the project b-…
A: The detailed solution of the given question is in Step 2.
Q: State the importance of Business Project and the types of it along with examples.
A: Small Introduction about Business Project A project is a group of tasks that must be completed. In…
Q: activity predecessor optimistic time(days) Most likely time(days) Pessimistic time(days) A - 4 8 24…
A: Find the Given details below: Activity Predecessors Optimistic Time(To) a(Days) Pessimistic…
Q: Consider the following project activities: Activity Predecessor Duration (DAY) A…
A: Given data is
Q: 31) Use the values in the table to calculate activity durations and variances for the project. Which…
A: Network diagram: Calculation of expected time and variance with given Optimistic, pessimistic and…
Q: Q3: Determine the time completion of project for the activities shown below: H Activity. | A В С D E…
A: We have the given Activity starting from A to P Expected duration (weeks) Preceding activities
Q: 2. Draw the network on the basis of the most likely durations. Find critical path. Calculate the the…
A: Given information, Durations Activity IPA Optimistic Most likely Pessimistic A 4 6…
Q: Project ALPHA has 6 Acivities from A to Fas folows: Activity Duration Preceded By A 3 7 A 1 The Late…
A: Given: Activity Predecessors Duration A - 3 B A 9 C A 7 D B 5 E C 5 F E 1 Edge and…
Q: activity predecessor optimistic time(days) Most likely time(days) Pessimistic time(days) A - 4 8 24…
A: This question is related to the topic -Project Management and this topic fall under the Operations…
Q: Activity Description Duration (weeks) Precedent A Team Formation 1 B Project Planning 3 A Site…
A:
Q: Suppose the Prime Minister promised to complete the project within 50 days. What are the chances of…
A: Probability is simply the chances of the particular task getting completed on its expected time. The…
Q: Activity Time estimate (days) Succeeding Activity A 4 D A E F 11 C G H D,E,F 7 G
A: Network Diagram :
Q: Ql: For activities shown in table below, find the new time of project after updating, if the project…
A:
Q: Q2:Find out the completion time and the critical activities for the following project: D 20 B E H 11…
A: Project management is the management in which different types of skills and techniques are used to…
Q: Let us revisit the project data from Question 7 of Homework #2, where all times are in days (and it…
A: Given data is
Q: Q1: For activitics shown in table below, find the new time of project after updating, if the project…
A:
Q: Calculate ES, EF, LS, LF and slack for the following: Activity Task Predecessor Duration A Policies…
A: Given data is
Q: ) USING EXCEL ONLY: Construct the project network
A: Below is the solution:-
Q: 1) A list of activities, precedence relations, and optimistic, most likely, and pessimistic activity…
A: PLEASE BE NOTED THAT AS PER THE BARTLEBY POLICY I HAVE DONE THE FIRST QUESTION FOR ALL THE SEVEN…
Q: Activity 3: Scenarios of a project activities (tables given below) and their required times to be…
A: Note: Since you have posted a question with multiple subparts, we will solve the first three…
Q: The Omega department is planning to bid on large project for the development of a new communication…
A:
Q: Activity Predecessor Activity Time (month) 30 A 8 B 8 B 5 2 D,E 25 A 10 Η GG 3 5 A 5 1,J 15 F,K 2
A: a) The project network is as follows:
Q: Q1: Determine the duration of project for the activities shown below, and find the critical path by…
A: Given data is
Q: 1. The duration of project 2. The critical path by using (Activity on Nodemethod) - A-O-N Activity…
A: Given Information:
Q: All activity times are in days. 1. What is the expected project completion time ? ( in days) 2.…
A: Note - Hi! Thank you for the question, As per the honour code, we are allowed to answer three…
Q: Draw AON diagram showing ES EF, LS and LF; then find how long is the project to take? b) What is…
A: THE ANSWER IS AS BELOW:
Q: Example: - 02) Activities of a project with estimates of activity times are listed below. Activity…
A: In order to calculate the expected time, the following formula is used. Expected time =Optimistic…
Q: Activity Immediate Optimistic Most Likely Pessimistic Predecessor A 7 8 9 B 10 10 13 A 8 10 13 11 14…
A: Solution The expected completion time is given by - E=O+4M+P6 where O is optimistic time, M is most…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Q: Activity Relationships Activity Duration Logic A 5 Start В 7 Start C 3 B SS1 D 4 A SS2 , FF2 ;C FSo…
A:
Q: Table 7.4 Activity Predecessor Time(weeks) 8. B 6. 4. D A 11 B 3 G D, E, F 1 1) Using Table 7.4,…
A: 1) The earliest time for completion for this project is 20 weeks so the answer is C)20 weeks
Q: Using the table below, the Late Finish (LF) of activity C is: Activity P M Predecessor A 22 22 10…
A: Given data is
Q: 15. Answer the questions that follow based on the output below (note: times are in weeks). Project…
A: “Since you have asked multiple question, we will solve the first question for you. If you want any…
Q: Activity A BEDCFGHI 5 5 2 3 3 4 5 5 6 Duration (days) Following B,D,E C,F F F,G G G H,I R R Activity…
A:
Q: Thank youuu
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Draw a Project Network and determine the critical path of this project? Activity Description…
A: Given data is
Q: 1. Determine the amount of slack in each of a proiect's activities (presented below), and identify…
A: Formula:
Q: 1. When will the activity be finished? 9 months 10 months 11 months 1 year 2. When will activity…
A: This question is related to the topic- project management and this topic fall under the operations…
Q: Activity Duration (day) Predecessor (s) Act. A 2 Act. B 3 Act. C 3 А Act. D 4 В Act. E 3 C,D Act. F…
A: Find the given details below: Given Details: Activity Duration(Days) Predecessor A 2 - B 3…
Q: Activity Immediate Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b)…
A: Given Information: Activity Immediate Predecessors Optimistic Time (a) Most Likely Time…
Q: 6. Suppose you are given the following data for a project: Activity Expected Activity Time (in days)…
A:
Q: Activity Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost (S)…
A: Activity Normal Normal Crash Crash Immediate Duration (hours) Cost ($) Duration (hours) Cost (S)…
Q: (a) Calculate the probability that the project will be completed in 31 weeks. (Round your answer to…
A: The critical path is the path that takes the longest time among all the other paths to complete the…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 3 images
- 14. Stephanie, the supply chain analyst of Nestle is asked to present an expansion plan for thecompany. The plan is either to construct a plant, open a distribution center, or do nothing. Fromthe plant construction, the company will gain 80,000Php if the market turns favorable, loss of10,000 if average, and loss of 50,000 if unfavorable. From opening a distribution center, thecompany will gain 40,000Php if favorable, gain 20,000Php if average, and loss of 30,000Php ifunfavorable. And if the decision is do nothing, the company will gain nothing regardless of themarket turnout. Then, he was able to determine further the probability of occurrence of eachtype of market. The probability of occurrence is 60%, 25%, and 40%, respectively. He also foundout that he can buy the information on what will really happen to the market for 2,000Php.a. What should be the analyst’s decision?b. How much gain or loss will he expect for the company?c. Should he buy the perfect information? Why or why not?d.…Please create an objective true using these two solutions. Solution1 - More accommodation/residence should be built in the airport itself as it would allow Pascal to save a lot of time consumed while reaching the airport from his house. He would stay in the built-in residence only during his workdays and in his house on the weekend. It will also allow many passengers to stay if their flights get postponed/canceled due to any reason. Solution 2 - If a prayer room/area is built in the airport itself, it will allow Rajput and other diverse travelers and people who work in the airport to complete their prayer in its proper time. Rajput could complete that specific prayer between the time after he checks in his luggage and the boarding time. PLEASE FOLLOW THESE REQUIRMENTS ASWELL OTHERWISE QUESTION WILL BE MARKED INCOMPLETE: Three levels of objectives are included. At the 1st-level, three or more objectives are included. Each 1st-level objective is broken into two or more 2nd-level…The table below contains information about an environmental clean-up project in the township of Hiles. Shorten the project threethree weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs. Activity Normal Time (weekweeks) Crash Time (weekweeks) Cost to Crash ($ per weekweek) Immediate Predecessor(s) A 55 44 300300 None B 77 44 5050 None C 77 66 300300 A D 77 66 250250 A E 11 11 long dash— B F 33 33 long dash— C, D G 55 44 200200 D, E H 44 22 200200 F I 22 22 long dash— G Part 2 Fill in the table below with the activity times after crashing to show the resulting schedule. (Enter your responses as…
- Projects W, X, Y, and Z are each being screened according to four criteria:Potential Return on Investment, Lack of Technological Risk, Environmental“Friendliness,” and Service to Community:• Project W: Return, high; Risk, medium; Environment, medium; Service, low• Project X: Return, medium; Risk, high; Environment, medium; Service, low• Project Y: Return, medium; Risk, medium; Environment, high; Service, high• Project Z: Return, medium; Risk, medium; Environment, high; Service, low.Create a scheme for screening the projects, assuming equal weight for all criteria.Which project comes out best; which word explain the output of scope with help of figure. How risk been evauted while describing the scope management.10.6 This optional problem requires knowledge of statistics. Heywood Home Healthcare is evaluating a project with the following net cash flows and probabilities: Time 0 Year 1 Year 2 Year 2 Year 3 Year 4 Prob = 0.2 ($100,000) 20,000 20,000 20,000 20,000 30,000 Prob = 0.6 ($100,000) 30,000 30,000 30,000 30,000 40,000 Prob = 0.2 ($100,000) 40,000 40,000 40,000 40,000 50,000 The year 5 values include salvage value. Heywood’s corporate cost of capital is 10 percent. What is the project’s expected NPV on the basis of the scenario analysis? What is the project’s standard deviation of NPV? Assume that Heywood’s managers judge the project to have lower-than-average risk. Furthermore, the company’s policy is to adjust the corporate cost of capital up or down by 3 percentage points to account for differential risk. Is the project financially attractive?The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…
- Jaronda is a member of a dance team. As a fundraiser, she and the other members of the team decide that she will use the team's money to buy flowers in bulk, sell the flowers individually to students with her school's permission, and return the team's money plus any profits she makes, What is the MOST accurate name for aronda's role? O A. project manager © B. network facilitator O C data manager O D. systems operatorDiana are currently employed as full-time supervisor at a wealth management company in Kuala Lumpur, and she want to negotiate with the head manager, Mrs. Janice to work flexible hours from home on long term bases due to her condition which have previously miscarriage for two times. She is worried about her current pregnancy which just entered the second month. She and her husband has been waiting to conceive for more than 4 years. However, Diana want to implement this flexible hour (work remotely) to everyone in the company. Diana want to work remotely because she is now having to take care of herself as according to the doctor, she is so fragile at the early of her pregnancy. She must reduce her steps to make sure no bleeding could happen. Since she was on work from home mode for the last month as she is given bed rest by the doctor, she seems to prefer working in such condition. Diana found that working remotely gave her the flexibility and was able to concentrate a lot more…Yreek International Limited an international Distribution Firm is currently seeking to fill the position of Director of Distributions as the current Director has resigned his position. The organization has had a rich history of promoting persons from within the organizations to fill vacant positions and this has worked successfully for them in the past. The Human Resources Manager Ms. Austen Whyte is having a discussion with Mrs. Kay Ferguson the General Manager regarding filling the vacant position. Ms. Austen believes that she should promote the current Distribution Manager who has three (3) year of experience in the position. Mrs. Ferguson however disagrees, and her view is to hire ‘fresh blood’ and bring new talent within the organization. Mrs. Ferguson also brought to the fore the functions of HRM and in particular ensuring that the organization is fully staffed and motivated. The efficient handling of the staffing function is very critical to organizations, and it may be the…
- As Jerry met with his executives to discuss the situation, the general manager, Tracy Lee, provided more information. She described the hotel as mainly targeting the upscale and luxury business market segments (75 percent), while also attracting the upscale and luxury leisure market segments (25 percent). The hotel’s main competitors are Four Seasons, J.W. Marriott, Shangri La, Mandarin Oriental, Landmark Hotel, and Conrad Hotel, which are all located within a two-mile radius. There is fierce competition among the hotels in this market segment, and firms have resorted to price-cutting tactics during economic downturns before. The products and services of the Great Eastern Hotel have been unique and of high quality. Guests have been particularly satisfied with the ambience of the hotel given that it has focused only on its core market segments for business. The rooms have been designed and appointed to satisfy its market segments. In fact, there has been a coherence among product…As Jerry met with his executives to discuss the situation, the general manager, Tracy Lee, provided more information. She described the hotel as mainly targeting the upscale and luxury business market segments (75 percent), while also attracting the upscale and luxury leisure market segments (25 percent). The hotel’s main competitors are Four Seasons, J.W. Marriott, Shangri La, Mandarin Oriental, Landmark Hotel, and Conrad Hotel, which are all located within a two-mile radius. There is fierce competition among the hotels in this market segment, and firms have resorted to price-cutting tactics during economic downturns before. The products and services of the Great Eastern Hotel have been unique and of high quality. Guests have been particularly satisfied with the ambience of the hotel given that it has focused only on its core market segments for business. The rooms have been designed and appointed to satisfy its market segments. In fact, there has been a coherence among product…As Jerry met with his executives to discuss the situation, the general manager, Tracy Lee, provided more information. She described the hotel as mainly targeting the upscale and luxury business market segments (75 percent), while also attracting the upscale and luxury leisure market segments (25 percent). The hotel’s main competitors are Four Seasons, J.W. Marriott, Shangri La, Mandarin Oriental, Landmark Hotel, and Conrad Hotel, which are all located within a two-mile radius. There is fierce competition among the hotels in this market segment, and firms have resorted to price-cutting tactics during economic downturns before. The products and services of the Great Eastern Hotel have been unique and of high quality. Guests have been particularly satisfied with the ambience of the hotel given that it has focused only on its core market segments for business. The rooms have been designed and appointed to satisfy its market segments. In fact, there has been a coherence among product…