Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 100. The projected demand, lot size, and time standards are shown in the following table: Item Touring bikes 6940 units/year Lot size 100 units Standard processing 0.25 hour/unit time Standard setup time 2 hours/lot Demand forecast Mountain bikes 6990 units/year 100 units 0.50 hour/unit 3 hours/lot The shop currently works 8 hours a day, 5 days a week, 50 weeks a year. If the shop maintains a 15 percent capacity cushion, how many workstations will be required next year to meet expected demand without using overtime?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter11: Simulation Models
Section: Chapter Questions
Problem 68P
icon
Related questions
Question
I need a step by step answer please :)
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a
variety of frame sizes, colors, and component combinations. Identical
bicycles are produced in lots of 100. The projected demand, lot size, and
time standards are shown in the following table:
Item
Touring bikes
Mountain bikes
Demand forecast
6940 units/year
6990 units/year
Lot size
100 units
100 units
0.50 hour/unit
Standard processing 0.25 hour/unit
time
Standard setup time 2 hours/lot
3 hours/lot
The shop currently works 8 hours a day, 5 days a week, 50 weeks a year.
If the shop maintains a 15 percent capacity cushion, how many
workstations will be required next year to meet expected demand without
using overtime?
Transcribed Image Text:Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 100. The projected demand, lot size, and time standards are shown in the following table: Item Touring bikes Mountain bikes Demand forecast 6940 units/year 6990 units/year Lot size 100 units 100 units 0.50 hour/unit Standard processing 0.25 hour/unit time Standard setup time 2 hours/lot 3 hours/lot The shop currently works 8 hours a day, 5 days a week, 50 weeks a year. If the shop maintains a 15 percent capacity cushion, how many workstations will be required next year to meet expected demand without using overtime?
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning