Use the List of Activities to develop an AON/CPM/Network Diagram 2) Complete the Critical Path Method (CPM) computations on the diagram developed in Step 1 above to determine the Critical Path, Activity Dates, and Total Float for activities 3) Now using Microsoft Project or Project Libre (if both do not work, use Excel) to develop the Network Diagram for the Sample Project (assume project starts on September 1, 2021) 4) Add Resource Information to your schedule using the Resources Needed table provided for the Sample Project. 5) Perform Resource Leveling on your Project The following documents can be assembled into a single PDF file and uploaded: Scan the network diagram with the calculations (see step 1 and step 2 above) Print the Gantt Chart from Mircosoft Project or Project Libre (after adding resources in step 4 but without performing Resource Leveling) Print the Gantt Chart from Mircosoft Project or Project Libre (after performing Resource Leveling listed in Step 5 above) One-page conclusions including--project start date and end date; project duration and critical path calculated

Np Ms Office 365/Excel 2016 I Ntermed
1st Edition
ISBN:9781337508841
Author:Carey
Publisher:Carey
Chapter6: Managing Multiple Worksheets And Workbooks
Section: Chapter Questions
Problem 14RA
icon
Related questions
Question

1) Use the List of Activities to develop an AON/CPM/Network Diagram

2) Complete the Critical Path Method (CPM) computations on the diagram developed in Step 1 above to determine the Critical Path, Activity Dates, and Total Float for activities

3) Now using Microsoft Project or Project Libre (if both do not work, use Excel) to develop the Network Diagram for the Sample Project (assume project starts on September 1, 2021)

4) Add Resource Information to your schedule using the Resources Needed table provided for the Sample Project.

5) Perform Resource Leveling on your Project

The following documents can be assembled into a single PDF file and uploaded:

  1. Scan the network diagram with the calculations (see step 1 and step 2 above)
  2. Print the Gantt Chart from Mircosoft Project or Project Libre (after adding resources in step 4 but without performing Resource Leveling)
  3. Print the Gantt Chart from Mircosoft Project or Project Libre (after performing Resource Leveling listed in Step 5 above)
  4. One-page conclusions including--project start date and end date; project duration and critical path calculated
List of Activities
Duration
Activity Activity Name
Туре
Predecessor
(weeks)
Directory Project
Summary Task
2
Funds Secured
Task
Negotiate with other agencies
Task
4
2
Form advisory group
Task
4
5
Establish a data collection plan
Task
4
6
Collect data
Task
4
5
Write directory text
Task
4
6
Identify printer
Task
2
4
9
Agree on print contract
Task
2
8
|10
Print directory
Task
4
7,9
11
Agree to a distribution plan
Task
12
4
12
Organize distribution
Task
4
11
13
Distribute directory
Task
10,12
00
Transcribed Image Text:List of Activities Duration Activity Activity Name Туре Predecessor (weeks) Directory Project Summary Task 2 Funds Secured Task Negotiate with other agencies Task 4 2 Form advisory group Task 4 5 Establish a data collection plan Task 4 6 Collect data Task 4 5 Write directory text Task 4 6 Identify printer Task 2 4 9 Agree on print contract Task 2 8 |10 Print directory Task 4 7,9 11 Agree to a distribution plan Task 12 4 12 Organize distribution Task 4 11 13 Distribute directory Task 10,12 00
Resources Needed
Activity Activity Name
Resource Name
1
Directory Project
Funds Secured
PM
Negotiate with other agencies
PM
Form advisory group
PM
Establish a data collection plan
Editor
6
Collect data
Editor
7
Write directory text
Editor
Identify printer
Contract Specialist
9
Agree on print contract
Contract Specialist
10
Print directory
Printer
11
Agree on a distribution plan
PM
12
Organize distribution
Editor
13
Distribute directory
PM
4-
00
Transcribed Image Text:Resources Needed Activity Activity Name Resource Name 1 Directory Project Funds Secured PM Negotiate with other agencies PM Form advisory group PM Establish a data collection plan Editor 6 Collect data Editor 7 Write directory text Editor Identify printer Contract Specialist 9 Agree on print contract Contract Specialist 10 Print directory Printer 11 Agree on a distribution plan PM 12 Organize distribution Editor 13 Distribute directory PM 4- 00
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 2 images

Blurred answer
Knowledge Booster
Software cost estimation
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Np Ms Office 365/Excel 2016 I Ntermed
Np Ms Office 365/Excel 2016 I Ntermed
Computer Science
ISBN:
9781337508841
Author:
Carey
Publisher:
Cengage
Systems Architecture
Systems Architecture
Computer Science
ISBN:
9781305080195
Author:
Stephen D. Burd
Publisher:
Cengage Learning
COMPREHENSIVE MICROSOFT OFFICE 365 EXCE
COMPREHENSIVE MICROSOFT OFFICE 365 EXCE
Computer Science
ISBN:
9780357392676
Author:
FREUND, Steven
Publisher:
CENGAGE L