Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order 1 2 3 4 5 6 Job ▼ For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number). Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job A BCDEE с F Operation 1 (hours) 4 10 3 14 6 7 Operation 2 (hours) 8 5 11 14 1 12 D

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Using​ Johnson's rule for​ 2-machine scheduling, the sequence​ is:
 
Scheduled Order
Job
1
 
B
C
E
F
A
D
Part 2
2
 
F
C
A
D
B
E
Part 3
3
 
A
B
D
F
C
E
Part 4
4
 
E
D
C
B
F
A
Part 5
5
 
F
C
D
A
E
B
Part 6
6
 
D
C
F
B
E
A
Part 7
For the schedule developed using​ Johnson's rule, the total length of time taken to complete the six jobs​ (including the 2nd​ operation) =
enter your response here
hours ​(enter your response as a whole​ number).
 
...
 

Question content area right

Part 1
Six jobs are to be processed through a​ two-step operation. The first operation involves​ sanding, and the second involves painting. Processing times are as​ follows:
                                                                                 
Job
Operation 1​ (hours)
Operation 2​ (hours)
A
4
 
8
 
B
10
 
5
 
C
3
 
11
 
D
14
 
14
 
E
6
 
1
 
F
7
 
12
 

 

Using Johnson's rule for 2-machine scheduling, the sequence is:
Scheduled Order
1
2
3
4
5
6
Job
▼
▼
For the schedule developed using Johnson's rule, the total length of time
taken to complete the six jobs (including the 2nd operation) = hours
(enter your response as a whole number).
Six jobs are to be processed through a two-step operation. The
first operation involves sanding, and the second involves painting.
Processing times are as follows:
Job
OABCDEF
Operation 1
(hours)
4
10
3
14
6
7
Operation 2
(hours)
8
5
11
14
1
12
Transcribed Image Text:Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order 1 2 3 4 5 6 Job ▼ ▼ For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = hours (enter your response as a whole number). Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job OABCDEF Operation 1 (hours) 4 10 3 14 6 7 Operation 2 (hours) 8 5 11 14 1 12
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.