Question

A proposed embankment fill requires 8000 ?3 of compacted soil. The void ratio of 
the compacted fill is specified as 0.70. Four borrow pits are available as described in the table 
which list the respective void ratios of the soil and cost per cubic meter for moving the soil to the 
proposed construction site. Make necessary calculations to select pit from which the soils should 
be bought to minimize the cost. Assume specific gravity to be the same at all pits.

Void Ratio (e)
Cost Php/m3
400.00
Borrow Pit
A
0.82
В
1.1
250.00
C
0.9
450.00
0.78
600.00
Transcribed Image Text:Void Ratio (e) Cost Php/m3 400.00 Borrow Pit A 0.82 В 1.1 250.00 C 0.9 450.00 0.78 600.00
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Pricing excavation and backfill
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Recommended textbooks for you
Engineering Fundamentals: An Introduction to Engi…
Engineering Fundamentals: An Introduction to Engi…
Civil Engineering
ISBN:
9781305084766
Author:
Saeed Moaveni
Publisher:
Cengage Learning