were assigned as a pr manager TUr a Ilai projecCt in on. You est ה ןן ומך the plot will require somewhere between 10,000 square meters and 12,000 square meters of land. The building will have a foot print of 8,000 meters. The rest will be used for gardening and planting trees. You want to benefit from the current LBP conditions and would like the project to be done before 2025. You envision a five story building and a penthouse. The garden will include orange and cherry trees with some bushes. The building will have upscale electrical and mechanical finishing. The super structure will be made from RC with an outside cladding of natural stones. Many of the materials will be imported from outside the country and this might add extra risks due to the political and health conditions globally and in Lebanon. 1- Make all the assumptions you need to plan the project using the following activities: Excavation, foundation, super structure, electro mechanical works, finishing 2- Using justified one point estimates provide the overall duration of the project 3- Using a PERT distribution provide the estimate duration for the project 4- Estimate the duration of the first floor only then use learning curves to estimate the duration of

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
You were assigned as a project manager for a residential project in North Lebanon. You estimate that
the plot will require somewhere between 10,000 square meters and 12,000 square meters of land. The
building will have a foot print of 8,000 meters. The rest will be used for gardening and planting trees.
You want to benefit from the current LBP conditions and would like the project to be done before 2025.
You envision a five story building and a penthouse. The garden will include orange and cherry trees with
some bushes. The building will have upscale electrical and mechanical finishing. The super structure will
be made from RC with an outside cladding of natural stones. Many of the materials will be imported
from outside the country and this might add extra risks due to the political and health conditions
globally and in Lebanon.
1- Make all the assumptions you need to plan the project using the following activities: Excavation,
foundation, super structure, electro mechanical works, finishing
2- Using justified one point estimates provide the overall duration of the project
3- Using a PERT distribution provide the estimate duration for the project
4- Estimate the duration of the first floor only, then use learning curves to estimate the duration of
the project
5- Conduct research to estimate the cost of the following: Excavation, concrete (assume a total
quantity of (5,000 cubic meters), Gardening and landscape (Assume quantity of trees)
6- Conduct an economic assessment to evaluate the impact of various exchange rates on the NPV
and IRR of the project
7- Couple the previous part with your judgement to decide on whether this project should go on
Transcribed Image Text:You were assigned as a project manager for a residential project in North Lebanon. You estimate that the plot will require somewhere between 10,000 square meters and 12,000 square meters of land. The building will have a foot print of 8,000 meters. The rest will be used for gardening and planting trees. You want to benefit from the current LBP conditions and would like the project to be done before 2025. You envision a five story building and a penthouse. The garden will include orange and cherry trees with some bushes. The building will have upscale electrical and mechanical finishing. The super structure will be made from RC with an outside cladding of natural stones. Many of the materials will be imported from outside the country and this might add extra risks due to the political and health conditions globally and in Lebanon. 1- Make all the assumptions you need to plan the project using the following activities: Excavation, foundation, super structure, electro mechanical works, finishing 2- Using justified one point estimates provide the overall duration of the project 3- Using a PERT distribution provide the estimate duration for the project 4- Estimate the duration of the first floor only, then use learning curves to estimate the duration of the project 5- Conduct research to estimate the cost of the following: Excavation, concrete (assume a total quantity of (5,000 cubic meters), Gardening and landscape (Assume quantity of trees) 6- Conduct an economic assessment to evaluate the impact of various exchange rates on the NPV and IRR of the project 7- Couple the previous part with your judgement to decide on whether this project should go on
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.