What is the critical path? By how many weeks are we 90% sure of completing the project (along the critical path)?
Q: Calculate the critical path for this project The Critical path is _______________ and the project…
A: The critical path is the path that takes the longest time to complete the project network.
Q: The following table lists the activities for a small part of a project with various durations and…
A: PERT is the project management technique used to schedule the tasks flow and predict the completion…
Q: 13.39 Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1.000, is…
A: Earned Value (EV) is the sum of percentage completed multiplied by the task budget. The calculation…
Q: What is the To Complete Performance Index if the project budget is $8,000, 40% of the project has…
A: With the give data, the calculations with formula are: Budget at completion (BAC) = $8000
Q: What are the key traits and differences of Project and Review Technique (PERT)/Critical Path Method…
A: Project management is the management in which different types of skills and knowledge is used to…
Q: a. What is the expected completion time of the project? The expected completion time is days. (Enter…
A: Estimated completion time is the time that shows the expected time for completing the project. It…
Q: The following descriptions are always true of the critical path in a project EXCEPT: * Is the…
A: Project management is the implementation of procedures, strategies, expertise, knowledge, and…
Q: 44. What activities make up the critical path? In crashing this project, which activity is the first…
A: Project crashing is the process of reducing the activity duration using additional cost through…
Q: Describe the other impacts on the project, such as quality, resources and risks.
A: Risk is the possibility of uncertainty that affects the related material, resources, management, or…
Q: 2. Reduce job 3 by two days. ONo O Yes 3. Reduce job 5 by two days. Yes O No e. What is the…
A: Given Information: Critical Path:- 1-2-5-8-9-11 Expected Completion Time:- 26.5 days
Q: PERT assumes that individual task times can be modeled with what type of prob- ability distribution?
A: PERT assumes that individual task times can be modeled with the beta distribution.
Q: Question 37 How much slack is there in task A? Your Answer: Your Answer Question 38 If the crash…
A: Slack is the available time in a activity for delaying the project without affecting the total…
Q: Determine the critical path(s) and slack time for non-critical activities for the project as shown…
A: CPM stands for Critical Path Method, which was invented by DuPont and was first used in the chemical…
Q: What is a Pareto analysis, and how does a project manager use it during quality control?
A: The term Pareto analysis refers to the use of a statistical approach in the decision-making process…
Q: Gantt and PERT charts are mostly implemented during project phases. They can be used in order to…
A: Project planning is described as a process or means of completing a project within a specified…
Q: 15F - Estimate how long (total time in months from start to finish, not how many months remain -…
A: THE ANSWER IS AS BELOW:
Q: predictions regarding Tom's next move
A: Tom Bray was thinking about the present plan for getting work done as he looked across the cove at…
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: Using the diagram, find: The critical path. How long it will take to complete the project?
A: Activity Expected time A 10 B 7 C 5 D 7 E 11 F 3 G 5 Paths : A-C-F : 10 + 5 + 3 =…
Q: A chart that shows both the time and sequence for completing the activities in a project is?…
A: A chart that shows both the time and sequence for completing the activities in a project is a Gantt…
Q: e) The activity variance along the critical path is|weeks. (Round your response to two decimal…
A: The critical path is the longest path taken by project activities to complete the project in project…
Q: Case: Tom Bray Tom Bray was mulling over today’s work schedule as he looked across the bay at the…
A: Management by Wandering Around (MBWA) is a management style that employs an ad hoc approach and…
Q: PERT and CPM techniques are used to determine the "critical path" for completing a series of related…
A: The PERT and CPM techniques are used to determine the critical path and we could also determine the…
Q: For the project data shown in the table below. Find The expected time to complete 77 % of the…
A: Given data: To find the expected time to complete 77% of the project M=2*O P=3*0 Activity…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: Why does the project manager do resource leveling?
A: Resource leveling is a resource optimization strategy that determines when a project can be…
Q: Draw a PERT chart for making a breakfast of three-minute eggs, buttered toast, and Define the…
A: The PERT chart is as follows:
Q: (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying…
A: Below is the solution:-
Q: O A-B-D-F-G-H O A-C-E-H O A-B-D-E-H O A-C-E-F-G-H c. How many weeks will it take to complete the…
A: The critical path method is a project management tool that is used to help plan and schedule the…
Q: What is the critical path for the actvities and how many days will the project take?
A: Here is Your Step Wise Solution:
Q: What is the total cost on day 9? What is the total project duration? If activity B is delayed four…
A:
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: a) The expected (estimated) time for activity C is 12.00 weeks. (Round your response to two decimal…
A: To determine the Estimated time for any activity, we would use the below formula, the expected time…
Q: 1.Make a list of the major deliverables for the project and use them to develop a draft of the work…
A: Work breakdown structure is a system involved in project management that helps in breaking down a…
Q: 11- What is the time to complete the project that achieves the probability of its magnitude? 16.5
A: z-score is calculated as the difference between the expected duration of the project and the actual…
Q: The possibility of completing the project in less or equal time The critical path plus 2 weeks is 95…
A:
Q: What is the significance of the critical path?
A: The critical path method often called CPM is nothing but the assets utilization algorithm for…
Q: What can the project manager offer to other departments to make the situation a win-win?
A: A project manager is responsible for the smooth execution of the projects but it will be difficult…
Q: Consider the network presented in the following table. Calculate the slack for activity D. (Enter…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: critical path is __________ and the project duration is _____________
A: A network diagram is a graphical representation of a project which helps to identify the project…
Q: How do we estimate the likelihood of a project being finished by a certain date? In this…
A: Project Evaluation and Review Technique (PERT) is a technique for evaluating and reviewing projects.…
Q: What is the expected completion time? What is the critical path? What is the latest that Jersey…
A: A network diagram is visual diagram of activity relationship in a project which helps to identify…
Q: In reference to the attached activity precedence diagram and activity times shown. (Feel free to…
A: Slack time = Slack time is the time by which a activity can be delayed , without delaying the over…
Q: The project shown within details what is the possibility t finish the project in 38 days? And what's…
A: Given that: Activity a m b 1 to 2 2 7 8 2 to 3 5 6 9 2 to 4 3 7 8 2 to 5 4 5 6 3 to 6…
Q: What is the earliest completion time of the project? days
A: A project network diagram is the process of a project shown visually. It is a diagram that has boxes…
Q: As a project manager you have been given task to complete . discuss with a sketch the life circle of…
A: In a project board guide, if you happen to be in a position where you are trusted to oversee your…
Q: 1- The number of critical paths in the project is All options are incorrect O
A: One of the methods to find the longest duration that a project would take to complete is the…
What is the critical path?
By how many weeks are we 90% sure of completing the project (along the critical path)?
Step by step
Solved in 4 steps with 2 images
- What is the estimated expected (mean) time (in days) for activity C? What is the estimated expected (mean) time (in days) for activity C? 100 60 72 44 48An air filtration system for CFF Food Market was design within a certain time frame in order that the company would not be closed down by EPA. a. Create a table with at least 10 random numbers for pessimistic, most likely and optimistic time b. Use the variables to determine the Expected Time and Variance (show working) c. Assume a critical path, and variables on the path to determine the standard deviationState and describe some of the limitations of time study method ?
- Describe some of the limitations of time study method ?16. Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 3 2 $1,200 $1,850 — B 2 1 $2,000 $2,800 — C 1 1 $300 $300 — D 7 3 $1,400 $1,720 A E 6 3 $850 $1,000 B F 2 1 $4,250 $5,250 C G 4 2 $1,500 $2,200 D, E Part 2 a) Based on the given information regarding the activities for the project, the project completion date = ______ weeks Part 3 b) To reduce the duration of the project to 10 weeks at the least cost, the…Eng. Samer, the director of software development department at SUC, in the process of designing a program that the students can use easily in the job-finding process. In the table below you can find the activities required to program the mentioned software: ID description Predecessor optimistic time most likely time pessemestic time crash time normal cost crash cost A System analysis None 2 4 6 3 2000 2400 B system design None 1 2 3 1 2200 2800 C subsystem design None 1 2 9 3 500 500 D programming A 3 7 17 4 2300 2600 E documentation C 4 6 8 3 900 1200 F subsystem test D,B,E 1 2 9 2 3000 4200 G integration test F,E 2 4 6 2 1400 2000 Draw project Network plan (diagram), and identifying all possible paths.
- 16. Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s) A 3 2 $1,000 $1,600 — B 2 1 $2,100 $2,850 — C 1 1 $300 $300 — D 7 3 $1,300 $1,620 A E 6 3 $900 $1,125 B F 2 1 $4,250 $5,450 C G 4 2 $1,800 $2,300 D, E Part 2 a) Based on the given information regarding the activities for the project, the project completion date = _____weeks. B) To reduce duration to 10 weeks, The following is the order of what needs to be…Installing mufflers at the O'Sullivan Garage in Golden, Colorado, involves five work elements. Jill O'Sull ivanhas timed workers performing these tasks seven times, with the results shown in the following table: By agreement with her workers, Jill allows a 10% fatigue factor and a 10% personal-time factor, but no time for delay. To compute standard time for the work operatio n, Jill excludes all observations that a ppear to be unusual or nonrecurring. She does not want an error of mo re than ±5%.a) What is the standard time for the task?b) How many observations are needed to assu re a 95% confidence level?b) Error encompasses all those occasions in which a planned sequence of activities fails toachieve its intended outcome. Human errors are frequently basic blunders that can havedisastrous consequences for those responsible. As a project manager, you are required toarrange error- proofing to reduce the impact of human error. explain it briefly and include example
- q11) What is flextime an example of? a. Job rotation b. Work sharing c. Modified work scheduling d. Job sharing e. Modified workplace planning This multiple choice question from INTRODUCTION TO BUSINESS course.just write for me the final answer.Q1:243 A project manager should have many skills. Describe two of these skills by providing a scenario in your choice to show how your selected skills are necessary. A description of the scenario’s environment is required for a better understood of the project manager qualities.Case STUDY ANALYSIS CREATION OF A NEW PROJECT Our Head of quality (that we will call Mr L.) suggested that the company needed to improve the planning and scheduling of the machining and tooling department. All companies that have machine production do this, and we already had someone scheduling this department (Mr M.), but we needed someone that could do it much more in detail and ahead of time. Eventually, the supervisor of the machining department(Mr S.) was elected to be the best person for this job, so the CEO of the company decided that Mr M. had to train Mr S. and explain the method he followed for the planning. Mr M. is known to be someone that likes to work the way he wants to work! In other words, he is not known for being someone that listens to other people’s opinion, so Mr S. (much younger) had some difficulty getting information out of Mr M. This problem had been planned. In fact, before this project started there had been at least two separate meetings, one together with…