For one of the construction projects, draw the (PERT) network diagram and find the following:
What is the probability of completion of the
project in 17.5 months? *
Actv.
Duration (month)
a
b
5-10
4
5-15
4
10-20
4
4
7
10-25
10-30
4
5
15-25
3.5
5.5
7.5
15-30
3
20-35
9
12
25-35
5
30-35
60%
50%
100%
0%
Transcribed Image Text:What is the probability of completion of the project in 17.5 months? * Actv. Duration (month) a b 5-10 4 5-15 4 10-20 4 4 7 10-25 10-30 4 5 15-25 3.5 5.5 7.5 15-30 3 20-35 9 12 25-35 5 30-35 60% 50% 100% 0%
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Budget estimating
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,