You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Year 2 Year 0 - $51 -$101 $21 $42 Project A B Year 1 $25 $20 a. What are the IRRs of the two projects? b. If your discount rate is 4.6%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are the IRRs of the two projects? The IRR for project A is%. (Round to one decimal place.) The IRR for project B is %. (Round to one decimal place.) b. If your discount rate is 4.6%, what are the NPVs of the two projects? If your discount rate is 4.6%, the NPV for project A is $ *** Year 3 $21 $50 Year 4 $15 $59 million. (Round to two decimal places.) If your discount rate is 4.6%, the NPV for project B is $ million. (Round to two decimal places.) c. Why do IRR and NPV rank the two projects differently? (Select from the drop-down menus.) is measuring value creation, while is measuring return on NPV and IRR rank the two projects differently because they are measuring different things. investment. Because returns do not scale with different levels of investment, the two measures may give different rankings when the initial investments are different.

Intermediate Financial Management (MindTap Course List)
13th Edition
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Eugene F. Brigham, Phillip R. Daves
Chapter12: Capital Budgeting: Decision Criteria
Section: Chapter Questions
Problem 21P: Your division is considering two investment projects, each of which requires an up-front expenditure...
icon
Related questions
Question
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million):
Year 2
Year 0
- $51
- $101
$21
$42
Project
A
B
Year 1
$25
$20
a. What are the IRRs of the two projects?
b. If your discount rate is 4.6%, what are the NPVs of the two projects?
c. Why do IRR and NPV rank the two projects differently?
%. (Round to one decimal place.)
a. What are the IRRs of the two projects?
The IRR for project A is
The IRR for project B is
%. (Round to one decimal place.)
b. If your discount rate is 4.6%, what are the NPVs of the two projects?
If your discount rate is 4.6%, the NPV for project A is $
C
Year 3
$21
$50
Year 4
$15
$59
million. (Round to two decimal places.)
million. (Round to two decimal places.)
If your discount rate is 4.6%, the NPV for project B is $
c. Why do IRR and NPV rank the two projects differently?
(Select from the drop-down menus.)
is measuring return on
NPV and IRR rank the two projects differently because they are measuring different things. Vis measuring value creation, while.
investment. Because returns do not scale with different levels of investment, the two measures may give different rankings when the initial investments are different.
Transcribed Image Text:You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Year 2 Year 0 - $51 - $101 $21 $42 Project A B Year 1 $25 $20 a. What are the IRRs of the two projects? b. If your discount rate is 4.6%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? %. (Round to one decimal place.) a. What are the IRRs of the two projects? The IRR for project A is The IRR for project B is %. (Round to one decimal place.) b. If your discount rate is 4.6%, what are the NPVs of the two projects? If your discount rate is 4.6%, the NPV for project A is $ C Year 3 $21 $50 Year 4 $15 $59 million. (Round to two decimal places.) million. (Round to two decimal places.) If your discount rate is 4.6%, the NPV for project B is $ c. Why do IRR and NPV rank the two projects differently? (Select from the drop-down menus.) is measuring return on NPV and IRR rank the two projects differently because they are measuring different things. Vis measuring value creation, while. investment. Because returns do not scale with different levels of investment, the two measures may give different rankings when the initial investments are different.
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Present Value
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage