You requested a survey monument to be installed at STA 12+55.25’. The project manager calls you from the job site and informs you that the reclamation district is installing a new sewer manhole at that location and they had to move the monument 177 inches further down the center line (increasing station #). What is the new station of the monument?

Construction Materials, Methods and Techniques (MindTap Course List)
4th Edition
ISBN:9781305086272
Author:William P. Spence, Eva Kultermann
Publisher:William P. Spence, Eva Kultermann
Chapter4: The Building Site
Section: Chapter Questions
Problem 3RQ
icon
Related questions
Question

You requested a survey monument to be installed at STA 12+55.25’. The project manager calls you from the job site and informs you that the reclamation district is installing a new sewer manhole at that location and they had to move the monument 177 inches further down the center line (increasing station #). What is the new station of the monument?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Engineering standards and codes
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Construction Materials, Methods and Techniques (M…
Construction Materials, Methods and Techniques (M…
Civil Engineering
ISBN:
9781305086272
Author:
William P. Spence, Eva Kultermann
Publisher:
Cengage Learning