Which type of cost system, process or job order, would be best suited for each of the following: (A) TV assembler, (B) building contractor, (C) automobile repair shop, (D) paper manufacturer, (E) custom jewelry manufacturer? Give reasons for your answers.

(a)

To determine

Cost Accounting Systems

Cost accounting systems are used to measure, record, and report product costs. Managers use products costs for setting product costs, controlling setups, and developing financial statements. There are two types of Cost accounting systems; they are:

  • Job order costs, and
  • Process costs

To Identify: The suitable cost system (Job order costs or Process costs) for TV assembler.

Answer

Process cost system is best suitable for TV assembler.

Explanation

TV assembler is suitable for the process cost system because, the products are slightly standard and lose their identities as individual items.

(b)

To determine

To Identify: The suitable cost system (Job order costs or Process costs) for building contractor.

Explanation

Building contractor is suitable for Job order cost system because; the building cost can be identified with each job without great difficulty.

(c)

To determine

To Identify: The suitable cost system (Job order costs or Process costs) for automobile repair shop.

Answer

Job order cost is best suitable for automobile repair shop.

Explanation

 Automobile repair shop is suitable for Job order cost system because; the cost can be equitably recognized with each job.

(d)

To determine

To Identify: The suitable cost system (Job order costs or Process costs) for paper manufacturer.

Answer

Process cost system is best suitable for paper manufacturer.

Explanation

Paper manufacturer is suitable for Process cost system because, manufacturing paper process endless and the products are homogeneous.

(e)

To determine

To Identify: The suitable cost system (Job order costs or Process costs) for custom jewelry manufacturer.

Answer

Process cost system is best suitable for custom jewelry.

Explanation

Custom jewelry manufacturer is suitable for job order cost system because, most of the jewelry production consists of job orders only, and the costs can be rationally recognized with each job.

The Solution to Your Study Problems

Bartleby provides explanations to thousands of textbook problems written by our experts, many with advanced degrees!

Get Started

Additional Business Solutions

Find more solutions based on key concepts

Show solutions add

For a stock to be in equilibrium, what two conditions must hold?

Fundamentals of Financial Management, Concise Edition (MindTap Course List)

Describe the two spans of management.

Foundations of Business (MindTap Course List)

Which inventory method always follows the actual physical flow of merchandise?

College Accounting, Chapters 1-27 (New in Accounting from Heintz and Parry)

What reinvestment rate assumptions are built into the NPV, IRR, and MIRR methods? Give an explanation for your ...

Fundamentals of Financial Management, Concise Edition (with Thomson ONE - Business School Edition, 1 term (6 months) Printed Access Card) (MindTap Course List)

What is a lag measure? A lead measure?

Cornerstones of Cost Management (Cornerstones Series)

Find all the answers to your study problems with bartleby.
Textbook solutions plus Q&A. Get As ASAP arrow_forward