Question 1. Question : (TCO B) Using the network below and the additional information provided, find
(a) the crash cost per day per activity;
(b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and
(c) what the extra cost is to crash the project.
Activity Normal Time Crash Time Normal Cost Crash Cost
A 5 3 $300 $600
B 3 2 $250 $450
C 6 4 $400 $500
D 5 3 $150 $400

A.
Question 2. Question : (TCO E) The following information is …show more content…

It is behind schedule by 8 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed. For each of the project above, choose an appropriate schedule compression technique. Explain your choice. Question 5. Question : (TCO F) Given the following information, calculate the CV, SV, CPI, and SPI for this project. Also provide recommendations to improve the project’s performance if needed. Activity A: This activity is 60% complete, at a cost of $80,000. It is at the end of Week 5 of 8 and was projected to cost 200,000. Activity B: This activity is not started yet; it will start in 2 weeks. It is planned to cost $400,000. Its costs to date are $0. Activity C: This activity is complete. It was completed in 6 weeks; it was supposed to have been completed in 5 weeks. The original budget for this activity was $400,000; in the end, it cost $450,000. Activity D: This activity is 75% complete with an original budget of $200,000. Costs to date are $65,000, and the project is at the beginning of Week 3 of