2) Draw the schematic flow diagram for Sunwind and all Volvo plants. (Draw at abstract level not detailed level). Provides detail of distances and demand (quantity based on 1987 forecast) flow.

Ans) Demand of Sunwind is 1250/week = 1250*45 = 56250 units

The following table gives us the demand of each plant yearly for the year 1985 Plant | | Torslando | Kalmar | Ghent | Total | Year | 1985 | 17050 | 4525 | 12090 | 33665 | | % | 50.65% | 13.44% | 35.91% | 100% | Year | 1987 | 32919.947 | 8736.819 | 23343.23 | 65000 |

Depending on the percentage of share of each plant of the total in 1985, the same percentage is used to calculate the demand of each plant in 1987, as we know the total production of Volvo from all …show more content…

5. This helps in cutting the waste by cutting the excess capacity or inventory and removing the non value-added activities. 6. This will develop a close relationship with their suppliers, in a way they will get suppliers as a partner in the venture. 7. This will also encourage the suppliers to get themselves placed in and around the Sunwood plant so as to deliver the raw materials on time. 8. This system gets an in-plant representative who will be onsite in Sunwind on behalf of the suppliers whose main purpose is to plan and schedule the replenishment of the materials from the supplier hence even the forecasting is also taken care by him. 9. He also helps in designing ideas to help reducing cost and improve manufacturing processes and managing production schedules for suppliers, materials contractors and other subcontractors. 10. It also provides the best organizational structure needed to improve the supplier coordination by integrating the logistics, production and purchasing processes together.

The advantages of the Volvo if Sunwind go for JIT is same as the ones enjoyed by Sunwind on behalf of their supplies * This will develop a close relationship with Sunwind. * This system gets an in-plant representative who will be onsite in Volvo on behalf of the Sunwind whose main purpose is to plan and schedule the replenishment of the materials from the supplier hence even the