1. (SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY  IMMEDIATE PREDECESSOR(S) A ---- B ---- C ---- D ---- E A, B, D F B, C G A, C, D H E, F I E J G K F, G L H, I, K M I, J N H, J, K   The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (in days) A 11 B 7 C 13 D 9 E 10 F 9 G 12 H 8 I 6 J 4 K 7 L 6 M 5 N 7   a. Construct the project network diagram using Activity-on-Node (AON) approach.     b. Determine the earliest start (ES) time, earliest finish (EF) time, latest finish (LF) time, and latest start (LS) time for all project activities.                                                             c. Determine slack times for all project activities.                                                            d. Identify the critical path(s) in the project network.                                                       e. How long will it take to complete the entire project?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
icon
Concept explainers
Topic Video
Question
1. (SHOW YOUR COMPLETE WORK) The activities needed for a new project your company is undertaking are listed in the following table.

ACTIVITY 

IMMEDIATE PREDECESSOR(S)

A

----

B

----

C

----

D

----

E

A, B, D

F

B, C

G

A, C, D

H

E, F

I

E

J

G

K

F, G

L

H, I, K

M

I, J

N

H, J, K

 

The activity times were determined for the project, and were as below.

ACTIVITY

ACTIVITY TIME (in days)

A

11

B

7

C

13

D

9

E

10

F

9

G

12

H

8

I

6

J

4

K

7

L

6

M

5

N

7

 

a. Construct the project network diagram using Activity-on-Node (AON) approach.    
b. Determine the earliest start (ES) time, earliest finish (EF) time, latest finish (LF) time, and latest start (LS) time for all project activities.                                                            
c. Determine slack times for all project activities.                                                           
d. Identify the critical path(s) in the project network.                                                      
e. How long will it take to complete the entire project?                                                  
Expert Solution
steps

Step by step

Solved in 6 steps with 6 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.