2. Find the critical path. What is the earliest time that the project can be completed?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

How can we solve question 2?

Project Management
Consider the dependency matrix and the activity durations provided below.
Information providing activity
A1
A2
АЗ
А4
A5
А6
A7
A8
A9
A10
А1
A2
X
АЗ
X
А4
A5
X
А6
A7
A8
A9
A10
Activity
A1
A2
АЗ
А4
A5
А6
A7
A8
A9
A10
Time
4
8
1
12
4
7
6.
1. Build a project graph, visually depicting the evolution of this project.
2. Find the critical path. What is the earliest time that the project can be completed?
3. For each activity, compute the latest start time, the latest completion time, and the slack time.
Information receiving activity
Transcribed Image Text:Project Management Consider the dependency matrix and the activity durations provided below. Information providing activity A1 A2 АЗ А4 A5 А6 A7 A8 A9 A10 А1 A2 X АЗ X А4 A5 X А6 A7 A8 A9 A10 Activity A1 A2 АЗ А4 A5 А6 A7 A8 A9 A10 Time 4 8 1 12 4 7 6. 1. Build a project graph, visually depicting the evolution of this project. 2. Find the critical path. What is the earliest time that the project can be completed? 3. For each activity, compute the latest start time, the latest completion time, and the slack time. Information receiving activity
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Layout strategy
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.