14.15 Given the following vertical curve data: PVI at 7+ 25.712. L- 100 m. g -32 pa cent. g: - +1.8 percent, and elevation of PVI 210.440. compute the elevados the curve low point and even 20-m.stations 14.16 Given the following vertical curve data: PVI at 19 + 00, L- S00 fi, g- +25 per cent. g: -1 percent, and elevation at PVI 723.86 fi. compute the elevations of the curve sumnit und even full stations (that is, 100-ft even stations 14.17 You are given the following vertical curve data: g +3 percent, g;-I percen design speed = 110 km/hr (from Table 14.6, K = 90 m), PVI at 0 + 360.100, with elevation of 156.663 m. Compute the curve elevations at the high point (svmmit) the even 50-m stations.

Traffic and Highway Engineering
5th Edition
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Garber, Nicholas J.
Chapter15: Geometric Design Of Highway Facilities
Section: Chapter Questions
Problem 7P
icon
Related questions
Question
14.15 Given the following vertical curve data: PVI at7+ 25.712, L= 100 m. g-32 pa
cent. g2 = +1.8 percent, and elevation of PVI = 210.440, compute the elevadoes
the curve low point and even 20-m stations
14.16 Given the following vertical curve data: PVI at 19 + 00, L S00 fi, gi +25 per
=-I percent, and elevation at PVI = 723.86 fi. compute the elevations of the
cent. g2
curve sumnit und even full stations (that is, 100-ft even stations
14.17 You are given the following vertical curve data: g +3 percent, g-1 percen
design speed = 110 km/hr (from Table 14.6, K = 90 m), PVI at 0 +360.100, with
elevation of 156.663 m. Compute the curve elevations at the high point (svmmit):
the even 50-m stations.
Transcribed Image Text:14.15 Given the following vertical curve data: PVI at7+ 25.712, L= 100 m. g-32 pa cent. g2 = +1.8 percent, and elevation of PVI = 210.440, compute the elevadoes the curve low point and even 20-m stations 14.16 Given the following vertical curve data: PVI at 19 + 00, L S00 fi, gi +25 per =-I percent, and elevation at PVI = 723.86 fi. compute the elevations of the cent. g2 curve sumnit und even full stations (that is, 100-ft even stations 14.17 You are given the following vertical curve data: g +3 percent, g-1 percen design speed = 110 km/hr (from Table 14.6, K = 90 m), PVI at 0 +360.100, with elevation of 156.663 m. Compute the curve elevations at the high point (svmmit): the even 50-m stations.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Drainage of pavements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning