2. The following mass haul diagram applies to Problems (1)-(4). Cubic Yards (Sta 1+00, 500 CY) (Sta 16+00, 530 CY) (Sta 20+00, 530 CY) FHD=400' (Sta 22+00, 450 CY) EHD=700' (Sta 15+00, 450 CY), (Sta 25+00, 350 CY) (Sta 12+00, 200 CY) (Sta 5+00, 200 CY)- EHD=700' Notes: FHD=400' -CM2: Sta 11+50 CM1 Sta 6+00 (Sta 7+00, 100 CY) (Sta 11+00, 100 CY) EHD: Economical Haul Distance FHD: Free Haul Distance CY: Cubic Yards CM: Center of Mass Station (1) The unit cost of overhaul is $0.90/yd³-Sta. Based on the above mass haul diagram, what is the overall cost associated with overhaul (between Sta 1+00 and Sta 15+00)? (2pts) (2) Based on the above mass haul diagram, determine the overall amount of borrow (between Sta 1+00 and Sta 25+00). (2pts) (3) Based on the above mass haul diagram, determine the overall amount of waste (between Sta 1+00 and Sta 25+00). (2pts) (4) Indicate the haul direction on the above graph by using either "" and/or "—". (between Sta 1+00 and Sta 25+00) (1pt)

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter16: Budget Estimating
Section: Chapter Questions
Problem 4RQ: Prepare a typical bay estimate based on the following information: a. Bay size of 350 feet and a...
icon
Related questions
Question

Please answer the questions in the picture please

2.
The following mass haul diagram applies to Problems (1)-(4).
Cubic Yards
(Sta 1+00, 500 CY)
(Sta 16+00, 530 CY)
(Sta 20+00, 530 CY)
FHD=400'
(Sta 22+00, 450 CY)
EHD=700'
(Sta 15+00, 450 CY),
(Sta 25+00, 350 CY)
(Sta 12+00, 200 CY)
(Sta 5+00, 200 CY)-
EHD=700'
Notes:
FHD=400'
-CM2: Sta 11+50
CM1 Sta 6+00
(Sta 7+00, 100 CY)
(Sta 11+00, 100 CY)
EHD: Economical Haul Distance
FHD: Free Haul Distance
CY: Cubic Yards
CM: Center of Mass
Station
(1) The unit cost of overhaul is $0.90/yd³-Sta. Based on the above mass haul diagram, what is
the overall cost associated with overhaul (between Sta 1+00 and Sta 15+00)? (2pts)
(2) Based on the above mass haul diagram, determine the overall amount of borrow (between
Sta 1+00 and Sta 25+00). (2pts)
(3) Based on the above mass haul diagram, determine the overall amount of waste (between
Sta 1+00 and Sta 25+00). (2pts)
(4) Indicate the haul direction on the above graph by using either "" and/or "—". (between
Sta 1+00 and Sta 25+00) (1pt)
Transcribed Image Text:2. The following mass haul diagram applies to Problems (1)-(4). Cubic Yards (Sta 1+00, 500 CY) (Sta 16+00, 530 CY) (Sta 20+00, 530 CY) FHD=400' (Sta 22+00, 450 CY) EHD=700' (Sta 15+00, 450 CY), (Sta 25+00, 350 CY) (Sta 12+00, 200 CY) (Sta 5+00, 200 CY)- EHD=700' Notes: FHD=400' -CM2: Sta 11+50 CM1 Sta 6+00 (Sta 7+00, 100 CY) (Sta 11+00, 100 CY) EHD: Economical Haul Distance FHD: Free Haul Distance CY: Cubic Yards CM: Center of Mass Station (1) The unit cost of overhaul is $0.90/yd³-Sta. Based on the above mass haul diagram, what is the overall cost associated with overhaul (between Sta 1+00 and Sta 15+00)? (2pts) (2) Based on the above mass haul diagram, determine the overall amount of borrow (between Sta 1+00 and Sta 25+00). (2pts) (3) Based on the above mass haul diagram, determine the overall amount of waste (between Sta 1+00 and Sta 25+00). (2pts) (4) Indicate the haul direction on the above graph by using either "" and/or "—". (between Sta 1+00 and Sta 25+00) (1pt)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 1 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,