50 cubic feet of 2:2-1/2:4 (by weight) concrete are to be produced. The constituents have the following properties= Constituent SSD Density (pcf) Moisture Cement 197 Sand 164 5% excess Coarse Aggregate 2% deficit 168 What are the required order quantities if the design calls for 5.5 gallons of water per sack and 5% entrained air?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter11: Pricing Concrete Work
Section: Chapter Questions
Problem 4RQ
icon
Related questions
icon
Concept explainers
Question
50 cubic feet of 2:2-1/2:4 (by weight) concrete are to be produced. The constituents have the following properties:
Constituent
SSD Density (pcf) Moisture
Cement
197
Sand
164
5% excess
Coarse Aggregate
2% deficit
168
What are the required order quantities if the design calls for 5.5 gallons of water per sack and 5% entrained air?
Transcribed Image Text:50 cubic feet of 2:2-1/2:4 (by weight) concrete are to be produced. The constituents have the following properties: Constituent SSD Density (pcf) Moisture Cement 197 Sand 164 5% excess Coarse Aggregate 2% deficit 168 What are the required order quantities if the design calls for 5.5 gallons of water per sack and 5% entrained air?
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Pricing concrete work
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,