9-Critical activities are
Q: ath method regarding pl
A: In order to successfully complete a project, a lengthy list of tasks must be completed along the…
Q: 2.0 Give an example of Critical Path Analysis of one (1) Method.
A: Project management is the management in which different types of skills and knowledge are required…
Q: Title B: Strategic HRM in Aviation Instruction: Select an airline or an airport and cover the…
A: HRM in the airline industry plays an important role as it affects many people.
Q: 1- ES for Activity C, E, G. J 2- E.F for Activity B. H 3- L.S for Activity A. J
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: What is flextime an example of? a. Job rotation b. Work sharing c. Modified work scheduling d. Job…
A: Job rotation is the technique by which employers move employees through different jobs at the same…
Q: 35 objective type questions.docx QQ浏览器文件服务 4/7 (25) For the following Project Human Resource…
A: we'll answer the the first question since the exact one is wasn't specified. please submit a new…
Q: TOPIC: Assignment Method OBJECTIVES: MINIMIZE COST OR TIME ONLY 1 JOB IS ASSIGNED TO MACHINE…
A: Find the given details below: Given details: Job Machine M1 M2 M3 AB 19 24 10 CD 14 17 19…
Q: Activity Immediate Predecessors Time (weeks) A None A A D. C. BD 4. E.F 7 3.
A: Activity Predecessors Time A None 6 B A 3 C A 7 D C 2 E B,D 4 F D 3 G E,F 7
Q: 11- The greatest value of the resources needed by the project will be obtained during the course of…
A: The resource allocation depends on the dependencies of the activity on other activities.
Q: What is the role of the leader in just-in-time inventory theory?
A: Just-in-time inventory theory or lean manufacturing is a management strategy in which raw materials…
Q: -Continuation- Required: 1. Prepare journal entries to record the cost incurred in both blending…
A: Journal Entry: Every journal entry is indeed a record of a commercial transaction in such an…
Q: Maximize: z = 1250x + 3500y Constraints: 5x + 4y s 60 x + y 29 y - 3x s9 . Submit your activity as a…
A: MAX z = 1250x + 3500ysubject to5x + 4y <= 60x + y >= 9-3x + y <= 9and x,y >= 0
Q: Act Immediate Predecessor Duration Activity Description Relationship Lag (weeks) ID (weeks) Planning…
A: The precedence relationship diagram is as follows: The possible paths are: 1) P1 - P3 - D3 - D4…
Q: 06-For the last few days Mr. Yousaf is facing a problem related with the release of funds on the…
A: : Operations is an important base for every organization, whether in manufacturing, service, or…
Q: Using the information given,(a) Calculate the expected time for each of the projectactivities. (b)…
A: Given data is
Q: Q2(a) Choong Machinery specializes in developing grass cutting equipment. Mr Ahmad, who is an R&D…
A: Given data, Solution: Activity Immediate Predecessors Duration A - 6 B - 5 C A 3 D A 2…
Q: 1- 7- 8- Jobs (i-j)2 1-3 2-3 2-4 3-5 4-6 4-8 5-6 6-7 8. Duration s (in days) 10 18 5 10 12 18 10 8 4…
A: Jobs (i-j) Duration 1-2 10 1-3 18 2-3 5 2-4 10 3-5 12 4-6 18 4-8 10 5-6 8 5-7 4…
Q: Requirement 2. Ralph does not like the idea of sharing the costs equally because he plans to stay in…
A: Given information: Costs and Allocation Allocation B R Costs Food Eaten (in pounds) 16 34…
Q: Problem 2: A large aerospace manufacturer is planning to propose a sophisticated drone for induction…
A: Based on the time estimate and the predecessor relationships given, we prepare a project network…
Q: Write down 5 important things/considerations when writing a Activity 3. research topic/problem.
A: A research problem is the main organizing principle which guides in analysis of the paper.
Q: Activity Predecessor(s) Duration (Months) 1. Proposal 2. Client meeting 3. Develop airframe spec. 4.…
A:
Q: T F Management functions occur according to arigid, preset timetable.
A: Management is referred to as a combination of various functions like planning, organizing, staffing,…
Q: From the following sales persons tasks, identify the tasks related to product servicing. a.…
A: General duties of the salesperson: helping customers with questions or inquiries about products and…
Q: I need help with 12.13. Chapter 12, problem 13.
A: a)Develop a master schedule for revised plan:
Q: 8. The following information (in AOA format) concerns progress at day 40 of an Internet marketing…
A: The overall project does not seem to be in control based on time and cost: Activity 1-2: This…
Q: c) Discuss SIX (6) resource management pitfall in the project.
A: The management is a cycle of preparation, dynamic, arranging, driving, inspiration, and controlling…
Q: Name some of the widely used project managementsoftware programs.
A: Project Management Software will be programming utilized by a broad scope of businesses for project…
Q: Activity Immediate Predecessor Time (Weeks) A -- В A C A 4 D A 4 E В C, D D, F F 6 G H D 3 E, G, H 3
A:
Q: 8. How many written days notice must you give an owner before you leave a rented apartment.* A one…
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Q: Questions: 1. Are there any barriers to execution? Explain 2. Can these barriers be addressed…
A: A company never works in isolation and is always influenced by various factors around it. These…
Q: Prerequisite A B A D D E Task Duration A. High Level Analysis 1 B. Selection of Hardware Platform 1…
A: Project network diagram is the visual representation of the project activities and their respective…
Q: Activity IPA Lag Duration Activity IPA Lag Duration 2 C A 2 D, E 10 A 2 E, F, G 8 3 7 7 В, С 4 K Н,…
A:
Q: 17. Objectives are both targets and A) Barriers B) Measuring sticks C) Threats D) Priorities E) Flow…
A: There are many methods to measure the quality of the product or service. Quality management is…
Q: Activity Case 1: Medina Company: The Change of Management Medina Company is the leading bus company…
A: Management of Business Managing the business transactions and the activities of a business, how to…
Q: The best technique to identify the timeframe of project activities and the possible logical flow of…
A: Program Evaluation Review Technique PERT is a method for examining the tasks involved in completing…
Q: 448 Activity D F 24. Office Automation, Inc., developed a proposal for introducing a new…
A:
Q: UESTION 11 Henry, a sales representative, set a goal of getting fifteen new accounts in the next…
A: Training programs are educational programs that are designed so that the employees can enhance their…
Q: Th e dean of the business school wants to start off eringthis program starting 32 weeks from now.…
A: Probability is the extent to which an event is likely to occur. It is computed by dividing the…
Q: QUESTION 16 planning focuses on determining the day-to-day activities necessary to achieve the…
A: Planning is a part of management function that focuses on forecasting the business activities to…
Q: ACTIVITY: Essay 1. Some companies market their products without first identifying their target…
A: Answer: The first statement of the question says that some companies market their products without…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G HA student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities “a” and “b” start on day 0. Draw the network diagram. Calculate ES/EF/LS/LF and Slack for all activities. Activity A: Immediate Predecessprs (-) Duration days (3) Activity B: Immediate Predecessprs (-) Duration days(5) Activity C: Immediate Predecessprs (a) Duration days(3) Activity D: Immediate Predecessprs (b) Duration days(7) Activity E: Immediate Predecessprs (C,D) Duration days(3)For conducting a project seven activities should be performed but maximum availablemanpower is 17. Task duration and manpower requirement is given below. Project managersaid, “It is possible to complete the project without leveling the manpower". Evaluate thestatement of the PM. (Justified or Not-Justified)
- Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?Using the information provided in the table, the network diagram and the project completion time = 25 weeks, reduce the completion time of the project by 3 weeks in the most economical way. Activity NormalTime(weeks) NormalCost ($) CrashTime(weeks) CrashCost ($) MaximumweeksReduced CrashCost perWeek ($) A 3 500 2 900 1 400 B 4 600 3 700 1 100 C 6 800 3 1,286 3 162.00 D 6 1,500 4 2,150 2 325 E 6 1,750 4 2,250 2 250 F 5 1,200 5 1,200 0 0 G 7 1,500 5 1,794 2 147 H 3 500 3 500 0 0 Reduce G by select a number of (1-4) week(s), C by select a number (1-4) of week(s), at a cost of $ __________ enter a dollar amount .
- Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersYou may need to use the appropriate technology to answer this question. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown. Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 5 6 B 2 4 6 C A, B 4 5 6 D A, B 8 10 11 E B 2 4 6 F C 1 2 3 G D 4 8 10 H D, F 7 9 11 I E, G, H 3 4 5 (b) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (c) Based only on the critical path, what is the estimated probability that the project can be completed in 27 or fewer days? (Round your answer to four decimal places.)
- Hi, I need help answering the last question. Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 5 3 $800 $1,200 - B 6 5 $300 $450 - C 6 5 $550 $775 - D 3 2 $750 $950 A E 6 3 $1,350 $2,250 C F 5 3 $675 $875 B What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)The following represents a very simple project. The calendar allows for 5 work days (M-F) per week. To keep things simple we won’t separate capital expenses and labour. The cost per activity shown below is total (i.e. not per day). Activity Duration (days) Precedent Cost A 5 None* $500 B 7 None* $1000 C 3 A , B $400 D 4 C** $500 E 6 C** $800 * Except for ‘Start’ ** The project can only be signed off once D and E have been completed. Enter the data into a software tool such as GanttProject, and generate the Gantt chart. Please ensure that: 1.…please help, project management. I need part D,Eand 2 1) Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV=$22,000 EV=$20,000 AC=$25,000 BAC=$120,000 a) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? Show your calculations. b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Explain. c) Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Explain. d) Use the SPI to estimate how long it will take to finish this project. e) Sketch the earned value chart for this project. 2) Write a one-page summary explaining how is project cost management different when using an Agile approach? Make sure to document any cited…