TABLE 16-15 Optimistic Time Pessimistic Time Estimates Estimates Estimates (weeks) Most Likely Time Immediate Activity Description of Activity Predecessor(s) (weeks) (weeks) Design general curriculum requirements Develop program brochure Identify prospective students Develop advertising campaign Design specific curriculum content Send brochure and student application Evaluate applications Accept students, notify students A none 4 8 16 B A 2 3 none 3 6 9 В, с 4 7 10 A 8. 16 20 F D 2 3 4 F 2 H. G 1 2 3 I Schedule rooms for classes H 1 1 7 Designate professors to teach courses H 3 K Select texts for courses 3 5 7 L Order and receive texts K 6 8 17 FIGURE 16-21 Network diagram Normal Crash E Immediate Time Normal Time Crash

Management, Loose-Leaf Version
13th Edition
ISBN:9781305969308
Author:Richard L. Daft
Publisher:Richard L. Daft
Chapter19: Managing Quality And Performance
Section: Chapter Questions
Problem 3CFCA: Cousins Jeri Lynn De Bose, Tish Hoover, and Josephine (Joey) Parks looked forward to meeting up...
icon
Related questions
Question

Th e dean of the business school wants to start off ering
this program starting 32 weeks from now. Using the information
provided in Problem 15,
(a) Calculate the probability of the program starting on
time.
(b) If the dean needs a 95 percent probability of being done
on time, how long can the expected project duration be?

TABLE 16-15
Optimistic
Time
Pessimistic
Time
Estimates Estimates Estimates
(weeks)
Most
Likely Time
Immediate
Activity Description of Activity
Predecessor(s) (weeks)
(weeks)
Design general curriculum requirements
Develop program brochure
Identify prospective students
Develop advertising campaign
Design specific curriculum content
Send brochure and student application
Evaluate applications
Accept students, notify students
A
none
4
8
16
B
A
2
3
none
3
6
9
В, с
4
7
10
A
8.
16
20
F
D
2
3
4
F
2
H.
G
1
2
3
I
Schedule rooms for classes
H
1
1
7
Designate professors to teach courses
H
3
K
Select texts for courses
3
5
7
L
Order and receive texts
K
6
8
17
FIGURE 16-21
Network diagram
Normal
Crash
E
Immediate
Time
Normal
Time
Crash
Transcribed Image Text:TABLE 16-15 Optimistic Time Pessimistic Time Estimates Estimates Estimates (weeks) Most Likely Time Immediate Activity Description of Activity Predecessor(s) (weeks) (weeks) Design general curriculum requirements Develop program brochure Identify prospective students Develop advertising campaign Design specific curriculum content Send brochure and student application Evaluate applications Accept students, notify students A none 4 8 16 B A 2 3 none 3 6 9 В, с 4 7 10 A 8. 16 20 F D 2 3 4 F 2 H. G 1 2 3 I Schedule rooms for classes H 1 1 7 Designate professors to teach courses H 3 K Select texts for courses 3 5 7 L Order and receive texts K 6 8 17 FIGURE 16-21 Network diagram Normal Crash E Immediate Time Normal Time Crash
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Management, Loose-Leaf Version
Management, Loose-Leaf Version
Management
ISBN:
9781305969308
Author:
Richard L. Daft
Publisher:
South-Western College Pub