A bridge is to be constructed now as part of a new road. Engineers have determined that current traffic volume on the new road will justify a two-lane road and a bridge at the present time. Because of the uncertainty regarding future traffic, the time at which the additional two lanes will be required currently being studied. Two alternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $454,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $200,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $200,000 plus an extra $28,000 for every year that widening is delayed. For example, if future widening is done at the end of year 5, the cost of widening at that time will be equal to $200,000 + 5x(S28,000) = $340,000. The following estimates have been made of when widening to a four-lane bridge will be required: Pessimistic estimate Most likely estimate Optimistic estimate End of year 2 End of year 5 End of year 6 In view of these estimates, which alternative would you recommend? The MARR used by the highway department is 6% per year (a) Calculate the PW of costs for the different scenarios of Alternative 2 PWpessimistic (6%) $ thousand (Round to one decimal place.) PWmost likely (6%) = S thousand (Round to one decimal place.) PWoptimistic (6%) = $ thousand (Round one decimal place.)
A bridge is to be constructed now as part of a new road. Engineers have determined that current traffic volume on the new road will justify a two-lane road and a bridge at the present time. Because of the uncertainty regarding future traffic, the time at which the additional two lanes will be required currently being studied. Two alternatives are being considered. Alternative 1 - One-stage construction: Build a four lane bridge right now for $454,000. Alternative 2 - Two-stage construction: Start with a two-lane bridge now for $200,000 and widen to four lanes later when traffic justifies. The future cost of widening the bridge to four-lanes at that time will be $200,000 plus an extra $28,000 for every year that widening is delayed. For example, if future widening is done at the end of year 5, the cost of widening at that time will be equal to $200,000 + 5x(S28,000) = $340,000. The following estimates have been made of when widening to a four-lane bridge will be required: Pessimistic estimate Most likely estimate Optimistic estimate End of year 2 End of year 5 End of year 6 In view of these estimates, which alternative would you recommend? The MARR used by the highway department is 6% per year (a) Calculate the PW of costs for the different scenarios of Alternative 2 PWpessimistic (6%) $ thousand (Round to one decimal place.) PWmost likely (6%) = S thousand (Round to one decimal place.) PWoptimistic (6%) = $ thousand (Round one decimal place.)
Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 3E
Related questions
Question
6
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning