A bridge is to be constructed now as part of a new road. Engineers have determined that traffic density on the new road wil justify a two-lane road and a bridge at the present time. Because of unce regarding future use of the road, the time at which an extra two lanes will be required is currently being studied. The two-lane bridge will cost $210,000 and the four-lane bridge, it built initially, will cost $400,000. The future cost of widening a two-lane bridge to four lanes will be an extra $210,000 plus $23,000 year that widening is delayed The MARR used by the highway department is 15% per year. The following estimates have been made of the times at which the four-lane bridge will be required: Pessimistic estimate Most likely estimate Optimistic estimate 9 yours In view of these estimates, what would you recommend? List some advantages and disadvantages of this method of preparing estimates. Click the icon to view the interest and annuity table for descrete compounding when the MARR is 15% per year 4 years 5 years

ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN:9780190931919
Author:NEWNAN
Publisher:NEWNAN
Chapter1: Making Economics Decisions
Section: Chapter Questions
Problem 1QTC
icon
Related questions
Question
A bridge is to be constructed now as part of a new road. Engineers have determined that traffic density on the new road will justify a two-lane road and a bridge at the present time. Because of uncerta.
regarding future use of the road, the time at which an extra two lanes will be required is currently being studied.
The two-lane bridge will cost $210,000 and the four-lane bridge, it built initially, will cost $400,000. The future cost of widering a two-lane bridge to four lanes will be an extra $210,000 plus $23,000 for
year that widening is delayed The MARR used by the highway department is 15% per year. The following estimates have been made of the times at which the four-lane bridge will be required:
4 years
Pessimistic estimate
Most likely estimate
5 years
9 years
Optimistic estimate
In view of these estimates, what would you recommend? List some advantages and disadvantages of this method of preparing estimates
Click the icon to view the interest and annuity table for discrete compounding when the MARR is 15% per year.
Calculate the PW value for the Pessimistic Estimate for the two-lane bridge
PW (15%)-S thousand (Round to one decimal place.)
Transcribed Image Text:A bridge is to be constructed now as part of a new road. Engineers have determined that traffic density on the new road will justify a two-lane road and a bridge at the present time. Because of uncerta. regarding future use of the road, the time at which an extra two lanes will be required is currently being studied. The two-lane bridge will cost $210,000 and the four-lane bridge, it built initially, will cost $400,000. The future cost of widering a two-lane bridge to four lanes will be an extra $210,000 plus $23,000 for year that widening is delayed The MARR used by the highway department is 15% per year. The following estimates have been made of the times at which the four-lane bridge will be required: 4 years Pessimistic estimate Most likely estimate 5 years 9 years Optimistic estimate In view of these estimates, what would you recommend? List some advantages and disadvantages of this method of preparing estimates Click the icon to view the interest and annuity table for discrete compounding when the MARR is 15% per year. Calculate the PW value for the Pessimistic Estimate for the two-lane bridge PW (15%)-S thousand (Round to one decimal place.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Knowledge Booster
Costs
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:
9780190931919
Author:
NEWNAN
Publisher:
Oxford University Press
Principles of Economics (12th Edition)
Principles of Economics (12th Edition)
Economics
ISBN:
9780134078779
Author:
Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:
PEARSON
Engineering Economy (17th Edition)
Engineering Economy (17th Edition)
Economics
ISBN:
9780134870069
Author:
William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:
PEARSON
Principles of Economics (MindTap Course List)
Principles of Economics (MindTap Course List)
Economics
ISBN:
9781305585126
Author:
N. Gregory Mankiw
Publisher:
Cengage Learning
Managerial Economics: A Problem Solving Approach
Managerial Economics: A Problem Solving Approach
Economics
ISBN:
9781337106665
Author:
Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:
Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-…
Managerial Economics & Business Strategy (Mcgraw-…
Economics
ISBN:
9781259290619
Author:
Michael Baye, Jeff Prince
Publisher:
McGraw-Hill Education