A company has a manufacturing plant that supply three markets in city A, B, and C. Management is looking for a place to locate a single distribution that will minimize total transportation costs. The plant is estimated to move (send) a total of shipment of 12,700 ton per month to the new distribution center. The transportation rate of moving shipment from the plant to the distribution center is $ 0.08 per ton per mile. Market A will receive a total shipment of 6,200 ton per month, market B will receive a total shipment of 2,000 ton per month, and market C will receive a total shipment of 4,500 ton per month. The transportation rate between the distribution center and the markets are as follows: $0.19 per ton per mile to market A, $0.37 per ton per mile to market B, and $0.25 per ton per mile to market C. The horizontal and vertical coordinates of the plants and markets are follows: Plant, 25, 75 Market A, 30, 5 Market B, 36, 24 Market C, 15, 40 Use the Center-of-Gravity method to find the location of the distribution center. Use at least 4 decimal places. The vertical coordinate of the new distribution center is.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter6: Optimization Models With Integer Variables
Section: Chapter Questions
Problem 100P
icon
Related questions
Question
A company has a manufacturing plant that supply three markets in city A, B, and C.
Management is looking for a place to locate a single distribution that will minimize
total transportation costs.
The plant is estimated to move (send) a total of shipment of 12,700 ton per month
to
the new distribution center.
The transportation rate of moving shipment from the plant to the distribution
center is $ 0.08 per ton per mile.
Market A will receive a total shipment of 6,200 ton per month,
market B will receive a total shipment of 2,000 ton per month, and
market C will receive a total shipment of 4,500 ton per month.
The transportation rate between the distribution center and the markets are as
follows:
$0.19 per ton per mile to market A,
$0.37 per ton per mile to market B, and
$0.25 per ton per mile to market C.
The horizontal and vertical coordinates of the plants and markets are follows:
Plant, 25, 75
Market A, 30, 5
Market B, 36, 24
Market C, 15, 40
Use the Center-of-Gravity method to find the location of the distribution center.
Use at least 4 decimal places.
The vertical coordinate of the new distribution center is
Transcribed Image Text:A company has a manufacturing plant that supply three markets in city A, B, and C. Management is looking for a place to locate a single distribution that will minimize total transportation costs. The plant is estimated to move (send) a total of shipment of 12,700 ton per month to the new distribution center. The transportation rate of moving shipment from the plant to the distribution center is $ 0.08 per ton per mile. Market A will receive a total shipment of 6,200 ton per month, market B will receive a total shipment of 2,000 ton per month, and market C will receive a total shipment of 4,500 ton per month. The transportation rate between the distribution center and the markets are as follows: $0.19 per ton per mile to market A, $0.37 per ton per mile to market B, and $0.25 per ton per mile to market C. The horizontal and vertical coordinates of the plants and markets are follows: Plant, 25, 75 Market A, 30, 5 Market B, 36, 24 Market C, 15, 40 Use the Center-of-Gravity method to find the location of the distribution center. Use at least 4 decimal places. The vertical coordinate of the new distribution center is
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,