A Company is in the process of preparing a budget for launching a new product. The following table provides the associated activities and their durations. Construct the project network and identify the critical path and its duration. Activity Predecessors Duration(wks) A: forecast sales volume - 10 B: study competitive market - 7 C: design item and facilities A 5 D: prepare production schedule C 3 E: estimate cost of production D 2 F: set sales price B,E 1 G: prepare budget E,F 14 (4) A project consists of the following activities, with the duration, in weeks, of each activity given in brackets. A(6), B(4) and C(7), the first activities of the project, can be executed concurrently. A and B precede D(2). B precedes E(1), F(5) and H(8). F and C precede G(3). E and H precede I(2) and J(4). C, F and J precede K(2). K precedes L(4).D, I, G and L are the terminating activities if the project. Construct the precedence table, and hence draw the network for the project Determine the critical path and the project duration for the project using the forward pass and the backward pass method.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

A Company is in the process of preparing a budget for launching a new product. The following table provides the associated activities and their durations. Construct the project network and identify the critical path and its duration. Activity Predecessors Duration(wks) A: forecast sales volume - 10 B: study competitive market - 7 C: design item and facilities A 5 D: prepare production schedule C 3 E: estimate cost of production D 2 F: set sales price B,E 1 G: prepare budget E,F 14 (4) A project consists of the following activities, with the duration, in weeks, of each activity given in brackets. A(6), B(4) and C(7), the first activities of the project, can be executed concurrently. A and B precede D(2). B precedes E(1), F(5) and H(8). F and C precede G(3). E and H precede I(2) and J(4). C, F and J precede K(2). K precedes L(4).D, I, G and L are the terminating activities if the project.

  • Construct the precedence table, and hence draw the network for the project
  • Determine the critical path and the project duration for the project using the forward pass and the backward pass method.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.