The following tasks must be performed on an
assembly line in the sequence and times specified.
Task
Task Time (seconds)
Tasks That Must
Precede
A
50
35
C
25
A
D
45
C
E
C
F
25
D
G
15
E
H
30
В, G
|
25
F, H
a) Draw the precedence diagram.
b) What is the cycle time to meet a forecasted
demand of 400 units per eight-hour day?
c) Balance the line to produce 400 units per day.
20
Transcribed Image Text:The following tasks must be performed on an assembly line in the sequence and times specified. Task Task Time (seconds) Tasks That Must Precede A 50 35 C 25 A D 45 C E C F 25 D G 15 E H 30 В, G | 25 F, H a) Draw the precedence diagram. b) What is the cycle time to meet a forecasted demand of 400 units per eight-hour day? c) Balance the line to produce 400 units per day. 20
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,